Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work

Expert replies
by silverflamein » Tue Nov 08, 2011 5:42 pm
Craig, Mark and Sue complete a certain piece of work in 10,20 and 5 hours respectively. Craig works alone for the first 2 hours. Mark and Sue then join Craig and the three complete the work together. How long did it take to complete the task ?

A - 3hrs

B - 3 4/7hrs

C - 4 hrs

D - 4 2/7 hrs

E - 4 5/7 hrs
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Tue Nov 08, 2011 5:59 pm
silverflamein wrote:Craig, Mark and Sue complete a certain piece of work in 10,20 and 5 hours respectively. Craig works alone for the first 2 hours. Mark and Sue then join Craig and the three complete the work together. How long did it take to complete the task ?

A - 3hrs

B - 3 4/7hrs

C - 4 hrs

D - 4 2/7 hrs

E - 4 5/7 hrs
Let the job = 20 units.
Rate for Craig = w/t = 20/10 = 2 units per hour.
Rate for Mark = w/t = 20/20 = 1 unit per hour.
Rate for Sue = w/t = 20/5 = 4 units per hour.
Work produced by Craig in 2 hours = r*t = 2*2 = 4 units.
Remaining work = 20-4 = 16 units.
Combined rate for C+M+S = 2+1+4 = 7 units per hour.
Time to finish the job = w/r = 16/7 hours.
Total time = 2 + 16/7 = 30/7 hours.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by neelgandham » Tue Nov 08, 2011 6:03 pm
Craig, Mark and Sue complete a certain piece of work in 10,20 and 5 hours respectively. Craig works alone for the first 2 hours. Mark and Sue then join Craig and the three complete the work together. How long did it take to complete the task ?

Craig can complete a work in 10 hours, So in 1 hour he can complete 1/10 th of the work.
Mark can complete a work in 20 hours, So in 1 hour he can complete 1/20 th of the work.
Sue can complete a work in 5 hours, So in 1 hour he can complete 1/5 th of the work.

Work completed in the first two hours = 2 * 1/10 = 2/10 = 4/20 - (1)
Mark and Sue then join Craig and say they completed the remaining work in h hours

Then

Work done during the first 2 hours + work done in the next H hours = 1 (1 unit of work)

4/20 + h*((1/10)+(1/20)+(1/5)) = 1, Implies
4/20 + h*((2/20)+(1/20)+(4/20)) = 1, Implies
4/10 + h*(7/20) = 1, Implies
h*(7/20) = 16/20
h = 16/7 = 2 2/7 hours

Total time taken to complete the tast is 2 + 2 2/7 = 4 2/7

Option D IMO
Anil Gandham
Welcome to BEATtheGMAT | Photography | Getting Started | BTG Community rules | MBA Watch
Check out GMAT Prep Now’s online course at https://www.gmatprepnow.com/
Join the discussion

by pemdas » Tue Nov 08, 2011 6:31 pm
their respective speeds are 1/10, 1/20 and 1/5 considering 1 as whole (or one work) and t (time required to complete work), 1/t
they will show average speed soon after Craig starts the job first and continues 2 h.: (1/10)*2
they will complete one job: (1/10)*2 + (1/10 + 1/20 + 1/5)*t=1
solve for t: 1/5+ t(2+1+4)/20=1, 4+7t=20, t=16/7 or Total time 16/7 h. Plus 2 h.= 4 2/7 h
d