BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Question 6 (nov. 15th)

Expert replies
by bacali » Sat Nov 15, 2008 4:59 pm
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete te job in 8 days?

A) 2
B) 3
C) 4
D) 6
E) 8

OA: B
Join the discussion
Source: — Problem Solving |


by cramya » Sat Nov 15, 2008 5:51 pm
6 machines takes 12 days to finish a job
1 machine will take 72 days

To finsih a job in 72 days 1 machine is needed
To finish a job in 8 days of of machines needed will be 72/8 = 9 machines

Differecne = 9-6 =3

3 additional machines needed
Join the discussion

by canuckclint » Sat Nov 15, 2008 6:56 pm
From the general formula:
6(1/x) = 1/12
Then for n more machines:
6/x + n/x = 1/8

Substitute:
1/12 + n/(12*6) = 1/8

n = 3