BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work Problem

Expert replies
Source: — Problem Solving |

by rey.fernandez » Sat Aug 09, 2008 9:28 pm
It's usually helpful with these problems to determine the rate of each machine.

All six machines take 12 days to do this job. If it were just one machine working at the job, it would take six times as long to finish the job, or 72 days.

If the job is to be completed in 8 days, then 72/8 = 9 machines to get the job done. This means 3 additional machines.
Rey Fernandez
Instructor
Manhattan GMAT
Join the discussion

by sudhir3127 » Sat Aug 09, 2008 9:29 pm
IMO B. 3.

Here it goes..

6 machines 1 day work = 1/12
therefore 1 machines 1 day work is 1/72

therefore that total number of machines required if we have a constraint on number of days (8) is 72/8 = 9 machines

hence the additional machiney is 9-6 ( we already have) = 3.

Hope it helps..
Join the discussion

by raunekk » Sat Aug 09, 2008 9:38 pm
6 mach = 12 days

therefore, 6 mach = 1/12 work / day...(1)


Let x be the number of additional machines required to do d work in 8 days.

so , (6+x)mach = 1/8 work / day ...(2)

cross multiply 1 and 2 to get x


thus, ( 6 + x) 1/12 = 6 / 8

thus x=3
Join the discussion

by ajmoney09 » Sat Aug 09, 2008 10:22 pm
Thanks guys for the help. Made me understand it for sure. Hopefully I get one of these in 10 days :) my math score is improving vastly, but I want to get my errors to so gle digits.. I got 13 today!! Close but no cigar!!