It's usually helpful with these problems to determine the rate of each machine.
All six machines take 12 days to do this job. If it were just one machine working at the job, it would take six times as long to finish the job, or 72 days.
If the job is to be completed in 8 days, then 72/8 = 9 machines to get the job done. This means 3 additional machines.
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
Redeem
Target Test Prep GMAT OnDemand
Scott Woodbury-Stewart’s private virtual classroom — 400 hours of master-class video lessons for the GMAT Focus Edition.
- 715+ score guarantee — highest in the industry (99th percentile)
- 52 chapters · 1,500+ lessons · 4,000+ practice questions
- 400 hours of video · 1,500+ instructor-led HD smartboard lessons
- 300,000+ students accepted to Harvard, Stanford, Wharton, Booth & Sloan & more
- 24/7 live support + weekly Zoom office hours with GMAT instructors
- TTP AI Assist — 24/7 AI-powered virtual tutor for instant help
- 1,200+ flashcards + AI-powered study assistant & daily calendar
- OnDemand, LiveTeach & GMAT Bootcamp formats available
- Also: GRE, SAT Math & Executive Assessment courses
- MBA Admissions Consulting now available
- 🏆 2025 EdTech Breakthrough Award: Test Prep Solution Provider of the Year
- 200,000+ students served
- 5-day free trial — $0 to start, no auto-billing, cancel anytime
★★★★★
5.0
(559 reviews)
130-pt guarantee
$0 to start
then $127/mo
Work Problem
Source: Beat The GMAT — Problem Solving |
IMO B. 3.
Here it goes..
6 machines 1 day work = 1/12
therefore 1 machines 1 day work is 1/72
therefore that total number of machines required if we have a constraint on number of days (8) is 72/8 = 9 machines
hence the additional machiney is 9-6 ( we already have) = 3.
Hope it helps..
Here it goes..
6 machines 1 day work = 1/12
therefore 1 machines 1 day work is 1/72
therefore that total number of machines required if we have a constraint on number of days (8) is 72/8 = 9 machines
hence the additional machiney is 9-6 ( we already have) = 3.
Hope it helps..
6 mach = 12 days
therefore, 6 mach = 1/12 work / day...(1)
Let x be the number of additional machines required to do d work in 8 days.
so , (6+x)mach = 1/8 work / day ...(2)
cross multiply 1 and 2 to get x
thus, ( 6 + x) 1/12 = 6 / 8
thus x=3
therefore, 6 mach = 1/12 work / day...(1)
Let x be the number of additional machines required to do d work in 8 days.
so , (6+x)mach = 1/8 work / day ...(2)
cross multiply 1 and 2 to get x
thus, ( 6 + x) 1/12 = 6 / 8
thus x=3
Thanks guys for the help. Made me understand it for sure. Hopefully I get one of these in 10 days