BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Doubt on Rate Problem

Expert replies
by bobdylan » Fri Apr 27, 2012 3:35 am
I really need some advice on these kind of questions:
1 Question: Six machines, each working at the same constant rate, can complete a job in 12 Days. How many additional machines, each working at the same constant rate, would be required to complete the task in 8 Days?
Solution posted on this site: one machine can do the work in 72 days, so you divide 72 by 8 to get 9. Then you subtract 9 by 6 in order to get 3 machines.

2 Question: 12 identical machines , running continuously at the same constant rate, take 8 days to complete a shipment. How many additional machines, each working at the same constant rate, would be needed to reduce the time required to complete a shipment by 2 days?
Solution on the Manhattan guide: The work of 12 machines is 12 r , so you multiply 12 r by 8 to get 96 r. To figure out how many machines are needed to complete this work in 8-2= 6 days, set up another row and solve for the unkown rate, getting 16 r. Thus, you need 16 machines in total, or 16-12= 4 additional machines.
My doubt is that the 2 look identical, but why you cannot apply the same methodology on both( if you do, the solutions are different)?????
Join the discussion
Source: — Problem Solving |

by niketdoshi123 » Fri Apr 27, 2012 4:36 am
1 Question: Six machines, each working at the same constant rate, can complete a job in 12 Days. How many additional machines, each working at the same constant rate, would be required to complete the task in 8 Days?
Solution:
As number of machines are inversely proportional to days, so if machines are reduced then number of days to complete a job will increase and vice-versa.
Image
So additional machines required = 9-6=3
Join the discussion

by niketdoshi123 » Fri Apr 27, 2012 4:45 am
2 Question: 12 identical machines , running continuously at the same constant rate, take 8 days to complete a shipment. How many additional machines, each working at the same constant rate, would be needed to reduce the time required to complete a shipment by 2 days?
Image
Additional machines required = 16-12 =4

Did the question the same way and solution is also same..
Join the discussion

by niketdoshi123 » Fri Apr 27, 2012 4:51 am
The work of 12 machines is 12 r
While doing a work-done problem always consider the work = 1 and not any variable such as 'r', this makes your job easier..
Join the discussion

by jrakhe » Fri Apr 27, 2012 3:46 pm
Rate and work problem can be solved using chart. As by using chart it is easy to know what is given and what is missing.
Join the discussion

by neelgandham » Sat Apr 28, 2012 12:13 pm
I am sure that you are not the only one to find work rate questions on the tougher side. To solve these questions easily, remember this work-rate mantra The value of Man(or Machine)-hours(or days) is always equal. What does this mean? It means - The product of the number of men/machines working and the number of work hours is always constant, given that the magnitude of work is constant. Let me solve question 1 using this.

Case 1:
Number of machines = M1 = 6
Number of days required to complete the job = D1 = 12

Case 2:
Number of machines = M2
Number of days the job should be completed in = D2 = 8

According to the above statement, M1*D1 = M2*D2. i.e 6*12 = 8*M2. The value of M2 = 9. So, we need M2-M1 = 9-6 machines to complete the task in 8 days.

Note: If the magnitude of work changes, then we cannot use the formula mentioned above. For example, If the question is 'Six machines, each working at the same constant rate, can complete a job in 12 Days.How many additional machines, each working at the same constant rate, would be required to complete 2 similar tasks in 8 Days?', we should tweak the formula.

(M1*D1)/W1 = (M2*D2)/W2, where W is the magnitude of Work.
6*12/1 = M2*8/2
M2 = 18. So. M2-M1 = 18-6 = 12 additional machines are needed to complete 2 similar tasks in 8 days.

Hope it helps. Let me know if you need any further help.
Last edited by neelgandham on Sat Apr 28, 2012 1:30 pm, edited 1 time in total.
Anil Gandham
Welcome to BEATtheGMAT | Photography | Getting Started | BTG Community rules | MBA Watch
Check out GMAT Prep Now's online course at https://www.gmatprepnow.com/
Join the discussion

by GMATGuruNY » Sat Apr 28, 2012 1:20 pm
bobdylan wrote:I really need some advice on these kind of questions:
1 Question: Six machines, each working at the same constant rate, can complete a job in 12 Days. How many additional machines, each working at the same constant rate, would be required to complete the task in 8 Days?
Solution posted on this site: one machine can do the work in 72 days, so you divide 72 by 8 to get 9. Then you subtract 9 by 6 in order to get 3 machines.

2 Question: 12 identical machines , running continuously at the same constant rate, take 8 days to complete a shipment. How many additional machines, each working at the same constant rate, would be needed to reduce the time required to complete a shipment by 2 days?
Solution on the Manhattan guide: The work of 12 machines is 12 r , so you multiply 12 r by 8 to get 96 r. To figure out how many machines are needed to complete this work in 8-2= 6 days, set up another row and solve for the unkown rate, getting 16 r. Thus, you need 16 machines in total, or 16-12= 4 additional machines.
My doubt is that the 2 look identical, but why you cannot apply the same methodology on both( if you do, the solutions are different)?????
Another approach is to plug in a rate for each machine.
I posted a solution to the first problem here:

https://www.beatthegmat.com/six-machines ... 52992.html

I posted a solution to a similar but more complex problem here:

https://www.beatthegmat.com/tv-assemble-t87042.html
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Danny@GMATAcademy » Sun Jan 08, 2017 10:04 pm
We can use the 'identical machines doing the same job' formula:

(old # of machines)(old time) = (new # of machines)(new time)

Plugging in, we get:

(12)(8) = (new #)(6)
(2)(8) = new #
16 = new #

So we need sixteen machines to do the job in 6 days. In other words we need 4 additional machines.

You can find an in-depth explanation of the formula used above here: https://www.youtube.com/watch?v=XOtwd6brDj8
Join the discussion