Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

X takes 10 days to complete a task. Y takes half that...

Expert replies
by AAPL » Tue Feb 20, 2018 6:44 am
X takes 10 days to complete a task. Y takes half that time to complete the same task. X starts working on the task and later Y joins X. Both work on the task together and complete the task. If 40% of the total work is done by X, for how many days did X and Y work together?

A. 2
B. 3
C. 4
D. 5
E. 6

The OA is B.

I don't have clear this PS question. I appreciate if any expert explains it to me. Thank you so much.
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Tue Feb 20, 2018 7:04 am
AAPL wrote:X takes 10 days to complete a task. Y takes half that time to complete the same task. X starts working on the task and later Y joins X. Both work on the task together and complete the task. If 40% of the total work is done by X, for how many days did X and Y work together?

A. 2
B. 3
C. 4
D. 5
E. 6
Let the task = 100 units.

Since Y's time is 1/2 X's time -- and X's time is 10 days -- Y's time to complete the 100-unit task is 5 days.
Thus, Y's rate = w/t = 100/5 = 20 units per day.
Since X produces 40% of the 100 units -- for a total of 40 units -- Y produces the remaining 60 units.
Since Y's rate = 20 units per day, the time for Y to produce 60 units = w/r = 60/20 = 3 days.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Jeff@TargetTestPrep » Thu Feb 22, 2018 8:38 am
AAPL wrote:X takes 10 days to complete a task. Y takes half that time to complete the same task. X starts working on the task and later Y joins X. Both work on the task together and complete the task. If 40% of the total work is done by X, for how many days did X and Y work together?

A. 2
B. 3
C. 4
D. 5
E. 6
We can let the number of days X worked alone = x and the number of days X and Y worked together = t. Since the rate of X is 1/10 and the rate of Y is 1/5, we have:

x(1/10) + t(1/10) = 2/5

and

x(1/10) + t(1/10 + 1/5) = 1

If we subtract the first equation from the second, we have:

t(1/5) = 3/5

t = 3

Answer: B

Jeffrey Miller
Head of GMAT Instruction
[email protected]