BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Working together, 7 identical pumps can empty a pool in 6 hours. How many hours will it take 4 pumps to empty the same

Expert replies
by AAPL » Fri Apr 30, 2021 5:37 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Magoosh

Working together, 7 identical pumps can empty a pool in 6 hours. How many hours will it take 4 pumps to empty the same pool?

A. 4 2/3
B. 9 1/4
C. 9 1/3
D. 9 3/4
E. 10 1/2

OA E
Join the discussion
Source: — Problem Solving |

Let the total amount of work required =42 units
In 6 hours work done =42 hours => so each hour work done =42/6 =7 unit /hr
since 7 pumps are working so total 1unit work per hour is done by each pump.
Hence 4 pumps will do 4 unit of work per hour
Total time required =42/4=21/2=10 1/2
Hence E.