BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Working simultaneously

Expert replies
by ska7945 » Tue Sep 02, 2008 8:35 pm
Working simultaneously and independently at an identical constant rate, 4 machines of a certain type can produce a total of x units of product P in 6 days. How many of these machines, working simultaneously and independently at this constant rate, can produce a total of 3x units of product P in 4 days?

A. 24
B. 18
C. 16
D. 12
E. 8

oa B
let's beat GMAT.
Join the discussion
Source: — Problem Solving |

by mehravikas » Tue Sep 02, 2008 9:41 pm
Plug in numbers for this problem.

Let x = 24

therefore, 4 machines produce 24 units in 6 days, that gives us 4 units per day for 6 days.

Case 1 -
Machines -> 4, Units -> 24, Days -> 6

Case 2 -
Machines -> M, Units -> 72 (remember 3x), Days -> 4

M = 72 / 4 -> M = 18

18 machines can produce 72 units in 4 days.
Last edited by mehravikas on Tue Sep 02, 2008 10:08 pm, edited 1 time in total.
Join the discussion

by P_mashru » Tue Sep 02, 2008 9:51 pm
Total work by 4 machines in 1 day - (1/6 + 1/6 + 1/6 + 1/6) x = 2/3 x

total work to be done - 3x, by 4 machines in 1 day = 9x /2x = 4.5 units

no of machines reuqured to do 3x work in 4 days = 4.5 x 4 = 18
I am I
Join the discussion

Re: Working simultaneously

by caloga » Sat Sep 06, 2008 1:21 am
4 machines--x units--6 days

4 machines--how many units?--4 days

how many units=y

y=4x/6=2x/3


how many machines--3x units--4 days

how many machines=z

z=12x/y=12x/(2x/3)=18
Join the discussion

by kshankker » Sat Sep 06, 2008 8:05 am
Hey this problem takes only 45 sec. Formula : amount = rate * work done
Given R1=R2:

step 1 : X= R1 * (4Machines * 6 days)
step 2 : 3X = R2* ( Y machines * 4 days )
step 3 : equate R1= R2
ie.. X/(4*6) = 3X/ (Y * 4)
Y = 18...

Hope you got it...........
Join the discussion

by sumithshah » Sat Sep 06, 2008 11:17 am
Simpler way ( I think )

4 machines do some work in 6 days
1 machine does it in 24 days.

24 days are needed to do some work by 1 machine
To do it in 4 days, we shall need : 6 machines.

To do thrice the work in 4 days, we shall need 18 machines.

I think the part where x and 3c comes in ( adding the 3rd variable ) simply kicks us in the head and confuses us. Essentially, its the same rate/work problems we've been doing in our heads all day long
Join the discussion

by Jeff@TargetTestPrep » Mon Dec 11, 2017 5:25 pm
ska7945 wrote:Working simultaneously and independently at an identical constant rate, 4 machines of a certain type can produce a total of x units of product P in 6 days. How many of these machines, working simultaneously and independently at this constant rate, can produce a total of 3x units of product P in 4 days?

A. 24
B. 18
C. 16
D. 12
E. 8
We are given that 4 machines can complete x units in 6 days. Thus, the rate of the 4 machines is x/6.
Next we need to determine the number of machines needed to produce a rate of 3x/4. To calculate that number of machines, we can use the following proportion in which the value in each numerator is the number of machines and the value in each denominator is the corresponding rate of those machines. We can let n = the number of machines needed:

4/(x/6) = n/(3x/4)

24/x = 4n/3x

72x = 4nx

18 = n

Answer: B