BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Working simultaneously and independently at an identical con

Expert replies
by mitzwillrockgmat » Mon May 24, 2010 4:43 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Working simultaneously and independently at an identical constant rate, 4 machines of a
certain type can produce a total of x units of product P in 6 days. How many of these
machines, working simultaneously and independently at this constant rate, can produce a
total of 3x units of product P in 4 days?

A. 24
B. 18
C. 16
D. 12
E. 8

Can someone break this down for me logically, in words. thanks :)
Join the discussion
Source: — Problem Solving |

by liferocks » Mon May 24, 2010 4:49 am
4 machines make x units in 6 days

so x units are prepared in 6*4 machine days
so 3x units are prepared in 3*6*4 machine days

if number of days is 4, number of machines will be 3*6*4/4=18

Ans option B
"If you don't know where you are going, any road will get you there."
Lewis Carroll
Join the discussion

by [email protected] » Sun Jun 17, 2018 7:43 pm
Hi All,

We're told that working simultaneously and independently at an identical constant rate, 4 machines of a certain type can produce a total of X units of product P in 6 days. We're asked for the number of machines that would be needed, working simultaneously and independently at this constant rate, to produce a total of 3X units of product P in 4 days?

When dealing with these types of 'work' questions, it's usually easiest to think in terms of the TOTAL amount of work needed to complete a job. If it takes 4 machines 6 days EACH to produce X units, then it takes...
(4 machines)(6 days each) = 24 machine-days of work to produce X units

Thus, 1 machine would need 24 days to produce X units
2 machines would need 12 days each to produce X units
3 machines would need 8 days each to produce X unites
Etc.

Now that we know how much work it takes to create X units, we know it takes 3(24) = 72 machine-days of work to produce 3X units. With a limit of just 4 days....
(Z machines)(4 days each) = 72 machine-days of work
Z = 72/4 = 18 machines needed to complete the job.

Final Answer: B

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by Scott@TargetTestPrep » Wed Jun 20, 2018 4:06 pm
mitzwillrockgmat wrote:Working simultaneously and independently at an identical constant rate, 4 machines of a
certain type can produce a total of x units of product P in 6 days. How many of these
machines, working simultaneously and independently at this constant rate, can produce a
total of 3x units of product P in 4 days?

A. 24
B. 18
C. 16
D. 12
E. 8
We are given that 4 machines can complete x units in 6 days. Thus, the rate of the 4 machines is x/6.

Now, we need to determine the number of machines needed to produce a rate of 3x/4. To calculate that number of machines, we can use the following proportion in which the value in each numerator is the number of machines and the value in each denominator is the corresponding rate of those machines. We can let n = the number of machines needed:

4/(x/6) = n/(3x/4)

24/x = 4n/3x

72x = 4nx

18 = n

Answer: B

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion

by Brent@GMATPrepNow » Fri Sep 07, 2018 7:20 am
mitzwillrockgmat wrote:Working simultaneously and independently at an identical constant rate, 4 machines of a
certain type can produce a total of x units of product P in 6 days. How many of these
machines, working simultaneously and independently at this constant rate, can produce a
total of 3x units of product P in 4 days?

A. 24
B. 18
C. 16
D. 12
E. 8

Can someone break this down for me logically, in words. thanks :)

Let's assign a nice value to x (a value that will work well with all of the numbers 3, 4 and 6.

Let's say x = 24

GIVEN: 4 machines make x units in 6 days
This means 4 machines make 24 units in 6 days
So, 4 machines make 4 units in 1 day [if you divide the work time by 6, the output is also divided by 6]
So, 1 machine makes 1 unit in 1 day [if you divide the number of machines by 4, the output is also divided by 4]

From here, we can answer the question How many of these machines, working simultaneously and independently at this constant rate, can produce a total of 3x units of product P in 4 days?
If x = 24, 3x = 72
Our goal is to make 72 units in 4 days.

So, 1 machine makes 4 units in 4 days [if you multiply the work time by 4, the output is also multiplied by 4]
So, 18 machines make 72 units in 4 days [if you multiply the number of machines by 18, the output is also multiplied by 18]

Answer: B

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com