BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Working alone at its constant rate, machine \(K\) took 3 hours to produce 1/4 of the units produced last Friday. Then

Expert replies
by M7MBA » Sun May 31, 2020 12:45 pm

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Working alone at its constant rate, machine \(K\) took 3 hours to produce 1/4 of the units produced last Friday. Then machine \(M\) started working and the two machines, working simultaneously at their respective constant rates, took 6 hours to produce the rest of the units produced last Friday. How many hours would it have taken machine \(M,\) working alone at its constant rate, to produce all of the units produced last Friday?

A. 8
B. 12
C. 16
D. 24
E. 30

[spoiler]OA=D[/spoiler]

Source: Official Guide
Join the discussion
Source: — Problem Solving |

3/4 of the production is left.
Together, both machines take 6 hours to complete 3/4 of the product

In those 6 hours, K can produce 2/4 of the product (1/4 * 2).
This means M produced 1/4 in 6 hours.

It would take M 6*4 hours to complete production alone. (D)
Join the discussion

M7MBA wrote:
Sun May 31, 2020 12:45 pm
Working alone at its constant rate, machine \(K\) took 3 hours to produce 1/4 of the units produced last Friday. Then machine \(M\) started working and the two machines, working simultaneously at their respective constant rates, took 6 hours to produce the rest of the units produced last Friday. How many hours would it have taken machine \(M,\) working alone at its constant rate, to produce all of the units produced last Friday?

A. 8
B. 12
C. 16
D. 24
E. 30

[spoiler]OA=D[/spoiler]

Source: Official Guide
Solution:


Since it takes machine K 3 hours to produce 1/4 of the units, machine K’s rate is (1/4)/3 = 1/12. If we let m be the number of hours it takes machine M to produce all the units by itself, then machine M’s rate is 1/m. Since it takes both machines 6 hours to produce the rest of the units (i.e., 3/4 of the units), we can create the equation:

(1/12 + 1/m) x 6 = 3/4

1/12 + 1/m = 1/8

1/m = 1/24

m = 24

Answer: D