Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work

Expert replies
by ketkoag » Fri Jun 19, 2009 5:07 pm
Working together, Jose and Jane can complete an assigned task in 20 days. However, if Jose worked alone and complete half the work then Jane takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Jose take to complete the task if he worked alone? Assume Jane is more efficient than Jose.
A. 25 days.
B.30 days.
C. 60 days.
D. 65 days
E. 36 days.

OA: C
Join the discussion
Source: — Problem Solving |

by cramya » Fri Jun 19, 2009 5:44 pm
let x and y be Jose and Jane's rate

Given xy/x+y = 20

xy = 20(x+y) (I)

x/2+y/2 = 45

x+y=90 (II)

xy = 1800

Solve for x using I and II
y=90-x

x(90-x) = 20(x+90-x)
x^2-90x+1800 = 0

(x cant be 30 since Jose is less efficient than Jane)


(OR)

plug in choices(I started with C since I saw 60 to be a factor of 1800 and then added 60+30 and got 20 days working together) and check x=60


C