BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

work rate

Expert replies
by maihuna » Tue Jul 28, 2009 11:22 am
GoodPuzzle:

A railway cutting 850m in length is to have a uniform depth of 4.5m ans its dimensions across the top and bottom are to be respectively 31.2m and 16.8m. If 450 tonnes are excavated on an avergae per day and 1 cubic meter weights 9/4 tonnes, how long the work require?

429 days
449 days
469 days
489 days
499 days
Charged up again to beat the beast :)
Join the discussion
Source: — Problem Solving |

by PussInBoots » Tue Jul 28, 2009 12:17 pm
459 days

4.5 * { (31.2 + 16.8) / 2 } * 850 m^3 * (9/4) tonn /M^3 would give the total amount of tonnes. Now just divide it by 450
Join the discussion

by prindaroy » Tue Jul 28, 2009 3:03 pm
I got 459 too, but apparently that's not one of the answers;

anyways here it is;

31.2+16.8/2 * 4.5 = area of trapezoid

24 * 4.5 = 108. So volume = 108 * 850

Weight = 108*850*9/4

Days to extract = (108*850*9/4)/450

= 459
Join the discussion

Re: work rate

by doclkk » Tue Jul 28, 2009 3:41 pm
maihuna wrote:GoodPuzzle:

A railway cutting 850m in length is to have a uniform depth of 4.5m ans its dimensions across the top and bottom are to be respectively 31.2m and 16.8m. If 450 tonnes are excavated on an avergae per day and 1 cubic meter weights 9/4 tonnes, how long the work require?

429 days
449 days
469 days
489 days
499 days
The numbers don't seem very gmatty ... ?
Join the discussion

by maihuna » Wed Jul 29, 2009 4:53 am
Yes 459 is correct one..
Its a prism question on base trapezoid. So found the volume using prism formulae...
Charged up again to beat the beast :)