BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

work rate

Expert replies
by mariah » Tue Feb 03, 2009 7:57 pm
Person A completed 1/4 of a certain work in two hours. Then A and B completed the remaining work in 4.5 hours. How long time will it take for B to complete the work independently?

oa is 16 but i think it not right



A and B need two hours to produce 3000 products. If B works at half of its rate, they need three hours to finish the same work. What A's rate?
Join the discussion
Source: — Problem Solving |

Re: work rate

by gaggleofgirls » Tue Feb 03, 2009 9:49 pm
mariah wrote:Person A completed 1/4 of a certain work in two hours. Then A and B completed the remaining work in 4.5 hours. How long time will it take for B to complete the work independently?

oa is 16 but i think it not right
If A alone does 1/4 of the job in 2 hours, then A will do 1 job in 8 hours for a rate of 1/8.

If A + B do 3/4 of the job in 4.5 hours, then together they will do 1 job in 6 hours for a rate of 1/6.

A + B = A + B

1/8 + B = 1/6

B = 1/6 - 1/8

B = 8/48 - 6/48 = 2/48 = 1/12
B can do 1 job alone in 24 hours.

-Carrie
Join the discussion

Re: work rate

by gaggleofgirls » Tue Feb 03, 2009 10:00 pm
mariah wrote:A and B need two hours to produce 3000 products. If B works at half of its rate, they need three hours to finish the same work. What A's rate?
A+B = 3000/2 = 1500 per hour

A + B/2 = 3000/3 = 1000 per hour

Here are two ways to solve it.

If A + B/2 is 500 less than A + B, then B must be making 500 less products per hour at half his rate, so B normally makes 2*500 = 1000 product per hour.

Then A + 1000 = 1500
A = 500

OR

A + B = 1500

A + B/2 = 1000
multiply both sides by 2 to get 2A+B = 2000

Now just line up the equations and subtract:
2A + B = 2000
-A + B = 1500
------------------
A = 500

So As rate is 500 per hour.

-Carrie
Join the discussion

by dimonya » Tue Feb 03, 2009 10:10 pm
daim official answer is wrong !! it is 24 hrs not 16!!


mistake is probably in the wording we are not interpreting it right
Join the discussion

by mariah » Wed Feb 04, 2009 4:23 am
1 oa must be 18
...to complete the job

2 getting 500 as well
Join the discussion

by gaggleofgirls » Wed Feb 04, 2009 5:05 am
mariah wrote:1 oa must be 18
...to complete the job
Wow, that wording is open to interpretation. I read it as "complete the entire job on his own," which would be the rate for 1 job, which is 24 hours.

But I can see (maybe) how it can be read as "complete the 3/4 of the job that A+B did together," which would be 3/4 of 24 hours = 18.

Where did the question come from?

-Carrie
Join the discussion

by mariah » Thu Feb 05, 2009 1:26 pm
from unoficial source :)