Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

work rate

Expert replies
by mariah » Tue Feb 03, 2009 7:57 pm
Person A completed 1/4 of a certain work in two hours. Then A and B completed the remaining work in 4.5 hours. How long time will it take for B to complete the work independently?

oa is 16 but i think it not right



A and B need two hours to produce 3000 products. If B works at half of its rate, they need three hours to finish the same work. What A's rate?
Join the discussion
Source: — Problem Solving |

Re: work rate

by gaggleofgirls » Tue Feb 03, 2009 9:49 pm
mariah wrote:Person A completed 1/4 of a certain work in two hours. Then A and B completed the remaining work in 4.5 hours. How long time will it take for B to complete the work independently?

oa is 16 but i think it not right
If A alone does 1/4 of the job in 2 hours, then A will do 1 job in 8 hours for a rate of 1/8.

If A + B do 3/4 of the job in 4.5 hours, then together they will do 1 job in 6 hours for a rate of 1/6.

A + B = A + B

1/8 + B = 1/6

B = 1/6 - 1/8

B = 8/48 - 6/48 = 2/48 = 1/12
B can do 1 job alone in 24 hours.

-Carrie
Join the discussion

Re: work rate

by gaggleofgirls » Tue Feb 03, 2009 10:00 pm
mariah wrote:A and B need two hours to produce 3000 products. If B works at half of its rate, they need three hours to finish the same work. What A's rate?
A+B = 3000/2 = 1500 per hour

A + B/2 = 3000/3 = 1000 per hour

Here are two ways to solve it.

If A + B/2 is 500 less than A + B, then B must be making 500 less products per hour at half his rate, so B normally makes 2*500 = 1000 product per hour.

Then A + 1000 = 1500
A = 500

OR

A + B = 1500

A + B/2 = 1000
multiply both sides by 2 to get 2A+B = 2000

Now just line up the equations and subtract:
2A + B = 2000
-A + B = 1500
------------------
A = 500

So As rate is 500 per hour.

-Carrie
Join the discussion

by dimonya » Tue Feb 03, 2009 10:10 pm
daim official answer is wrong !! it is 24 hrs not 16!!


mistake is probably in the wording we are not interpreting it right
Join the discussion

by mariah » Wed Feb 04, 2009 4:23 am
1 oa must be 18
...to complete the job

2 getting 500 as well
Join the discussion

by gaggleofgirls » Wed Feb 04, 2009 5:05 am
mariah wrote:1 oa must be 18
...to complete the job
Wow, that wording is open to interpretation. I read it as "complete the entire job on his own," which would be the rate for 1 job, which is 24 hours.

But I can see (maybe) how it can be read as "complete the 3/4 of the job that A+B did together," which would be 3/4 of 24 hours = 18.

Where did the question come from?

-Carrie
Join the discussion

by mariah » Thu Feb 05, 2009 1:26 pm
from unoficial source :)
Join the discussion