BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work/Rate Problems

Expert replies
by swerve » Tue Apr 28, 2020 11:25 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

A machine that produces stroopwafels operates for four hours. During the first hour the machine works at a constant rate. During the next two hours, it works at double that rate, and during the last hour it works at double its previous rate. If the machine produces X stroopwafels during the three first hours, then during the four hours the machine produces how many stroopwafels?

A. \(\dfrac{4}{5}X\)
B. \(\dfrac{9}{5}X\)
C. \(2X\)
D. \(\dfrac{9}{4}X\)
E. \(\dfrac{7}{3}X\)

The OA is B

Source: Economist GMAT
Join the discussion
Source: — Problem Solving |

Re: Work/Rate Problems

by Scott@TargetTestPrep » Fri May 01, 2020 3:17 am
swerve wrote:
Tue Apr 28, 2020 11:25 am
A machine that produces stroopwafels operates for four hours. During the first hour the machine works at a constant rate. During the next two hours, it works at double that rate, and during the last hour it works at double its previous rate. If the machine produces X stroopwafels during the three first hours, then during the four hours the machine produces how many stroopwafels?

A. \(\dfrac{4}{5}X\)
B. \(\dfrac{9}{5}X\)
C. \(2X\)
D. \(\dfrac{9}{4}X\)
E. \(\dfrac{7}{3}X\)

The OA is B

Source: Economist GMAT
We can let the rate of the machine during the first hour be 10 stroopwafels, and thus, the rate during the next two hour is 20 stroopwafels per hour, and the rate during the last hour is 40 stroopwafels. Therefore, during the first 3 hours, the machine produces 10 + 2 * 20 = 50 stroopwafels. We see that X = 50 and therefore, since the total number of stroopwafels produced during the four hours is 50 + 40 = 90, we see that this is 9/5 * X.

Answer: B