Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work rate problem

Expert replies
by selango » Sat May 29, 2010 3:12 am
Running at their respective constant rates,Machine x takes 2 days longer to produce w widgets than Machine Y.At these rates, if the two machines together produce 5/4w widgets in 3 days,how many days would it take machine X alone to produce 2w widgets?

A)4

B)6

C)8

D)10

E)12

OA E
Join the discussion
Source: — Problem Solving |

by gmatjedi » Sat May 29, 2010 3:54 am
x= rate of work
rate of work of machine x= 1 / x+2
rate of work of machine y= 1 / x
cumulative rate by formula:
1/machine 1 + 1/machine 2 = 1/ cumulative work

(1/(x+2)) +1/x =1/r

Key is to recognize that this is to make 1 widget

Working together, x and y make 5/4 widgets in 3 days
Need to figure out how many days x and y together make 1 widget
5/4 / 3 = 1/x
x=12/5 days to make 1 widget

replace r in equation above with 12/5 and solve for x

(x+x+2)/(x(x+2))=1/(12/5)
12/5 * (2x+2)/(x^2+2x) = 1
24x+24=5x^2+10x
(5x+6)(x-4)=0
x =4
so rate of x
is 1/(4+2) = 1 widget every 6 days
therefore 2 widgets in 12 days
Join the discussion

by sanju09 » Sat May 29, 2010 5:15 am
selango wrote:Running at their respective constant rates,Machine x takes 2 days longer to produce w widgets than Machine Y.At these rates, if the two machines together produce 5/4w widgets in 3 days,how many days would it take machine X alone to produce 2w widgets?

A)4

B)6

C)8

D)10

E)12

OA E
If Machine X alone takes n days to produce 2 w widgets, then it would take ½ n days to produce w widgets, and hence Machine Y alone would take ½ n – 2 days to produce w widgets. Working together they would take ½ n (½ n – 2) / (½ n + ½ n – 2) days to produce w widgets, or they would take ¼ n (n – 4) / (n – 2) days to produce w widgets; or they would take 5/4 × ¼ n (n – 4) / (n – 2) days to produce 5/4 w widgets.

Or 5/4 × ¼ n (n – 4) / (n – 2) = 3

Or 5 n (n – 4) = 48 (n – 2)

See through the choices, A is impossible, start from C, feel like going down, [spoiler]E works![/spoiler]
The mind is everything. What you think you become. –Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com
Join the discussion

by liferocks » Sat May 29, 2010 7:51 pm
I have used the options to reach the ans.
First let W=1..and the number of days x complets 2 machines is 2x..
So the question gives x and y completes 5/4=1+1/4 machines in 3 days
x completes 1 machine in x days and y in x-2 days

option 1>2x=4 or x=2..so x-2=0..this is the number of days for y..not possible ..eliminated
option 2> 2x=6..x=3..x-2=1..so in 3 days y makes 3 machines,,,eliminated
option 3>2x=8...x=4..x-2=2..so y makes in 3 days 3/2 machine>5/4 machines...eliminated
optiin 4>2x=10,x=5..x-2=3..so in 3 days x n y makes 1+1/5 machines<1+1/4...eliminated

option E is the choice.