Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work problem

Expert replies
by nadib002 » Mon May 09, 2011 2:27 pm
A, B and C can finish a piece of work in 30, 40, and 60 days respectively. 10 days after they started to work together B leaves. 4 days after B left, A leaves and C completes the remaining work. Find how many days C had worked altogether.

This is how i did it: Please let me know if there is another easier way of solving it:

rate of A = 1/30

rate of B = 1/40

rate of C = 1/60

Work completed by all 3 in 10 days is W = rate * time


(1/30 + 1/40 + 1/60) * 10 = 3/4


Work left to complete = 1-3/4 = 1/4


Since B left after 10 days, the remaining work will have to be finished by A + C

rate of A + C together = (1/30 + 1/60)

Work done by A+C = (1/30 + 1/60) * 4 = 1/5

Work Left for C to complete alone = 1/4 - 1/5 = 1/20

Time required for C to complete 1/20 work alone = rate of C * time = 1/60 * time

Therefore time required for C to complete the remaining , 1/20 of the work @ 1/60 = 3 days

Total days worked by C = 10 + 4 + 3 = 17 days
Last edited by nadib002 on Mon May 09, 2011 2:53 pm, edited 1 time in total.
Join the discussion
Source: — Problem Solving |

by djiddish98 » Mon May 09, 2011 2:46 pm
1/30 + 1/40 + 1/60 = Completion in 1 day when working all 3 together = 8/240 + 6/240 + 4/240 = 18/240 = 9/120 = 3/40.

They all work together for 10 days - 3/40 * 10 = 30/40 = 3/4 done before B leaves.

B leaves - now working at 1/30(2/60) + 1/60 = 3/60 = 1/20 per day.

Do that for 4 days so 4*(1/20) = 1/5 completed before A leaves.

3/4 + 1/5 = 19/20 completed. All that's left is C now, working 1/60 per day. Needs to complete 1/20 or 3/60 units, so add 3 more days.

I'm getting a total of 10 days + 4 days + 3 days = 17 days.
Join the discussion

by GMATGuruNY » Mon May 09, 2011 2:53 pm
nadib002 wrote:A, B and C can finish a piece of work in 30, 40, and 60 days respectively. 10 days after they started to work together B leaves. 4 days after B left, A leaves and C completes the remaining work. Find how many days C had worked altogether.
Let job = 120 units.

Rate for A = w/t = 120/30 = 4 units per day.
Rate for B = w/t = 120/40 = 3 units per day.
Rate for C = w/t = 120/60 = 2 units per day.

Combined rate for A+B+C = 4+3+2 = 9 units per day.
Over 10 days, work completed by A+B+C = r*t = 9*10 = 90 units.

Combined rate for A+C = 4+2 = 6 units per day.
Over 4 days, work completed by A+C = 6*4 = 24 units.

Remaining work = 120-90-24 = 6 units.
Time for C to finish = w/r = 6/2 = 3 days.

Total days for C = 10+4+3 = 17 days.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by nadib002 » Mon May 09, 2011 3:08 pm
Thank you all for replying

The answer is 17 days.

@Mitch

I saw that you plugged in numbers. I did it using algebra. When should one plug in numbers vs algebra?

Thank you
Join the discussion

by GMATGuruNY » Mon May 09, 2011 3:21 pm
nadib002 wrote:Thank you all for replying

The answer is 17 days.

@Mitch

I saw that you plugged in numbers. I did it using algebra. When should one plug in numbers vs algebra?

Thank you
The approaches are the same: each determines respective rates for A, B and C.
The key difference: by plugging in a value for the job, we can solve using only integer values. No messy fractions.
For most rate problems, I plug in a value for the job.
Use whichever approach you prefer.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion