BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work Problem

Expert replies
by vladmire » Wed Feb 18, 2009 6:30 am
Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?
Join the discussion
Source: — Problem Solving |

Re: Work Problem

by billzhao » Wed Feb 18, 2009 6:47 am
vladmire wrote:Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?
Assume the rate of Clarissa is rc and that of Shawna is rs:
From the question, we know that:

(rc+rs)=1/6...........................(1)
1/rc+5=1/rs..........................(2)

From (1) and (2), we can solve for rc.
rc=1/10, rs=1/15

So tc=10 hours, Clarissa needs 10 hours to complete the job by herself and Shawna needs 15 hours to complete the job by herself.
Yiliang
Join the discussion

by vladmire » Wed Feb 18, 2009 7:07 am
Clarissa needs 10 hours to complete the job by herself and Shawna needs 15 hours to complete the job by herself
In this case needs only Carissa at 10hrs. and Shawna at 15hrs to paint the house alone. Would put them working together to complete the painting of the house in 1 day and a hour, but the question stem says together they would complete the painting in 6 days or 144 hours.
Join the discussion

Re: Work Problem

by x2suresh » Wed Feb 18, 2009 7:44 am
vladmire wrote:Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?

Rc +Rs = Rsc

1/t-5 + 1/t = 1/6


6(2t-5)= t^2-5t
t^2-17t+30 = 0

t=15 or 2 (2 is ruled out.)

C can complete job in 10 days. S can complete job in 15 days.

I don't see the answer..

What is the source?