Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work Problem

Expert replies
by vladmire » Wed Feb 18, 2009 6:30 am
Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?
Join the discussion
Source: — Problem Solving |

Re: Work Problem

by billzhao » Wed Feb 18, 2009 6:47 am
vladmire wrote:Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?
Assume the rate of Clarissa is rc and that of Shawna is rs:
From the question, we know that:

(rc+rs)=1/6...........................(1)
1/rc+5=1/rs..........................(2)

From (1) and (2), we can solve for rc.
rc=1/10, rs=1/15

So tc=10 hours, Clarissa needs 10 hours to complete the job by herself and Shawna needs 15 hours to complete the job by herself.
Yiliang
Join the discussion

by vladmire » Wed Feb 18, 2009 7:07 am
Clarissa needs 10 hours to complete the job by herself and Shawna needs 15 hours to complete the job by herself
In this case needs only Carissa at 10hrs. and Shawna at 15hrs to paint the house alone. Would put them working together to complete the painting of the house in 1 day and a hour, but the question stem says together they would complete the painting in 6 days or 144 hours.
Join the discussion

Re: Work Problem

by x2suresh » Wed Feb 18, 2009 7:44 am
vladmire wrote:Whats the next step
I know the formula is 1/t1 + 1/t2 = 1/t t=total hours or days I guess of both people working.

Clarissa and Shawna working together can paint the exterior of a house in 6 days. Clarissa by herself can complete this job in 5 days less than Shawna. How long will it take Clarissa to complete the job by herself?

A.16 days
B. 17.5 days
C. 19 days
D. 18.5 days
E. 20 days

C + S = 6 right and S-5 = C :?

Rc +Rs = Rsc

1/t-5 + 1/t = 1/6


6(2t-5)= t^2-5t
t^2-17t+30 = 0

t=15 or 2 (2 is ruled out.)

C can complete job in 10 days. S can complete job in 15 days.