BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work problem

Expert replies
by hey_thr67 » Sun Jun 03, 2012 12:21 am
2 men and 7 boys can do a work in 14 days. 3 men and 8 boys can do the same work in 11 days. Then 8 men and 6 boys can do 3 times the work in how many days ?

A: 12
B: 21
C: 27
D: 15
E: 18


How can I approximate the answer fast ?
Join the discussion
Source: — Problem Solving |

by Anurag@Gurome » Sun Jun 03, 2012 12:54 am
hey_thr67 wrote:2 men and 7 boys can do a work in 14 days. 3 men and 8 boys can do the same work in 11 days. Then 8 men and 6 boys can do 3 times the work in how many days ?
2 men and 7 boys does 1/14 of the job in one day.
3 men and 8 boys does 1/11 of the job in one day.

Hence, in one day,
  • (2m + 7b) = 1/14
    (3m + 8b) = 1/11

    So, (2m + 7b)/(3m + 8b) = 11/14
    --> (28m + 98b) = (33m + 88b)
    --> 10b = 5m
    --> m = 2b
Hence, in one day one man works twice of a boy.

Now, (2m + 7b) = (4b + 7b) = 11b
And, (8m + 6b) = (16b + 6b) = 22b

As, 2men and 7 boys, i.e. 11 boys completes the work in 14 days, 8 men and 6 boys, i.e. 22 boys will complete the work in 14/2 = 7 days.

Hence, 8 men and 6 boys can do 3 times the work in 3*7 = 21 days.

The correct answer is B.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/
Join the discussion

by hey_thr67 » Sun Jun 03, 2012 7:03 pm
Thanks Anurag, is there any shorter way . I tend to commit calculation errors when I am specifically solving arithmatic problems