working independantly, Sophia can finish a certain job in hald the time Monica can. If sophia works alone at the job for 5 days and then Monica work 6 days to finish the remaining job. how many days will it take Sophia to finish the whole job ?
answer is 6
i dun get why ?????
thanks thanks
work problem !! plzz help !!!
This topic has expert replies
GMAT/MBA Expert
- Ian Stewart
- GMAT Instructor
- Posts: 2621
- Joined: Mon Jun 02, 2008 3:17 am
- Location: Montreal
- Thanked: 1090 times
- Followed by:355 members
- GMAT Score:780
Are you sure the answer is 6?charmaine wrote:working independantly, Sophia can finish a certain job in hald the time Monica can. If sophia works alone at the job for 5 days and then Monica work 6 days to finish the remaining job. how many days will it take Sophia to finish the whole job ?
answer is 6
i dun get why ?????
thanks thanks
Sophia needs half as much time as Monica needs to do the same amount of work. We know that 5 days of Sophia's work plus 6 days of Monica's work finishes the job. Well, Sophia could have done Monica's share of the job in half the time: 3 days. It should therefore take Sophia 5+3 = 8 days to finish the job.