WORK - Interesting problem

Expert replies
Source: — Problem Solving |

by outreach » Tue Mar 23, 2010 10:50 pm
m- work done by a man in a day
w- work done by a woman in a day

3m=(1/68)
m=(1/68*3)
5m=(5/68*3)


5w=(1/68)
w=(1/68*5)
3w=(3/68*5)

5m+3w=(5/68*3)+(3/68*5)
=(1/30)

answer is C
-------------------------------------
--------------------------------------
General blog
https://amarnaik.wordpress.com
MBA blog
https://amarrnaik.blocked/
Join the discussion

by thephoenix » Tue Mar 23, 2010 10:50 pm
3m=5w--->1m=5/3w--->5m=25w/3

5m+3w=25w/3+3w=34w/3

now eqn is 5w*68=34/3w*x(days)
--->x=30 days
Join the discussion

by alwayslulu » Mon Mar 29, 2010 3:15 pm
wow! I look both explanation and still don't understand how can u get 30 days? my head is spinning now. :(~

more clarification would be very much appreciated! :)

~Lulu
Join the discussion

by eaakbari » Tue Mar 30, 2010 12:01 am
Rate of work = 1/ time taken

or another way to look at it is if person takes t days to do one job
each day he is doing 1/t amount of work

So since 3 men took 68 days
3/x = 1/68

So 1/x = 1/(3*68)

In the same fashion 1/y = 1/(5*68)

Now since 5 men and 3 women are working

5/(3*68) + 3/(5*68)

On solving we get
1/30

hence each day they do 1/30 work

So they take 30 days in all
Hope this explains
Join the discussion

by thephoenix » Tue Mar 30, 2010 1:42 am
alwayslulu wrote:wow! I look both explanation and still don't understand how can u get 30 days? my head is spinning now. :(~

more clarification would be very much appreciated! :)

~Lulu
actually i made veru short....appologies

formula to remeber in such problems
M1*D1=M2*D2=work done
in such problems always try to convert in one catogery either boy or men or women( there will be always some hint in q)
in this one
Three men or five women can construct the wall in 68 days------>(gives us) 3m=5w( becoz there eff are same)
or 3m*68=5w*68--->3m=5w[using formula m1*d1=m2*d2]
from abve 1m=5w/3
so 5m+3w---->5(5w/3)+3w=34w/3
now again using the same formula
5w*68=34w/3*(say)x days---->solvingx=30 days
hth
Join the discussion

by alwayslulu » Tue Mar 30, 2010 10:02 am
thanks for the explanation.

M1*D1=M2*D2=work done . Is M men? and D days? what is the general formula? is it W = R.T or R= W.T ? i'm so confused


And when can i use this formula (A*B)/(A+B) ?