Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work - Four machines

Expert replies
by yass20015 » Mon Aug 10, 2015 2:00 pm
3 machines operating independently, simultaneously, a,d at the same constant rate can fill a certain production order in 36 hours. If one additional machine were used under the same operating conditions, in how many fewer hours of simultaneous operation could the production order be filled ?
Thanks!
Join the discussion
Source: — Problem Solving |

by Brent@GMATPrepNow » Mon Aug 10, 2015 2:13 pm
Here's the original question:
Three machines operating independently, simultaneously, and at the same constant rate can fill a certain production order in 36 hours. If one additional machine were used under the same operating conditions, in how many fewer hours of simultaneous operation could the production order be fulfilled?

A. 6
B. 9
C. 12
D. 27
E. 48
Let's assign some NICE values that satisfy the given conditions.
Let's say that EACH MACHINE produces 1 widget per hour.
So, 3 of the machines working together will produce 3 widgets per hour.

We're told that it takes 36 hour to complete the production order.

Output = (rate)(time)
= (3 widgets per hour)(36 hours)
= 108 widgets
So, the production order = 108 widgets.

IF WE ADD A MACHINE,HOW LONG WILL IT TAKE TO COMPLETE THE ORDER?
Since there are now 4 machines, their COMBINED rate = 4 widgets per hour
time = (output)/(rate)
= (108 widgets)/(4 widgets per hour)
= 27 hours

36 hours - 27 hours = 9 hours
So, it takes 9 fewer hours to complete the order.
Answer: B
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by GMATGuruNY » Mon Aug 10, 2015 2:22 pm
Three machines operating independently, simultaneously, and at the same constant rate can fill a certain production order in 36 hours. If one additional machine were used under the same operating conditions, in how many fewer hours of simultaneous operation could the production order be fulfilled?

A. 6
B. 9
C. 12
D. 27
E. 48
Use the following formula:
(machines)(time) = (machines)(time).

Since 3 machines require 36 hours, and 4 machines require x hours, we get:
(3)(36) = (4)(x)
x = 27.

Time decrease = 36-27 = 9 hours.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by yass20015 » Tue Aug 11, 2015 1:46 am
Thanks. I just found an easy algebric approach:

Lets a: the time needed by each machine to do the work alone.
3 machines need 36h: 1/a + 1/a +1/a = 1/36
we have 3/a = 1/36 so a = 3*36
4 machines need x hours: 4/a = 1/x so x = a/4 = 3*9 = 27

36 - 27 = 9