Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

work and work

Expert replies
by maihuna » Mon May 04, 2009 10:38 am
A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men , but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The no of men originally employed were:
3
4
5
6
9

A contractor employed 30 men to do a piece of work in 38 days, after 25 days he employed 5 men more and the work was finished one day earlier. how many days he would have been behind if he had not employed additional men:

1
5/4
3/2
7/4
2
Join the discussion
Source: — Problem Solving |

by PussInBoots » Mon May 04, 2009 12:03 pm
Are these trick questions?
#1: no of men originally employed has to be > 6 otherwise if 6 workers were absent from the very first day, project would not have been completed
But answer 9 is not correct either.

#2: I cannot even tackle this one. How could a contractor be behind a deadline more than 1 day if after hiring additional workers, the project was done 1 day earlier.
Join the discussion

Re: work and work

by Brent@GMATPrepNow » Mon May 04, 2009 4:12 pm
maihuna wrote:A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men , but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The no of men originally employed were:
3
4
5
6
9

A contractor employed 30 men to do a piece of work in 38 days, after 25 days he employed 5 men more and the work was finished one day earlier. how many days he would have been behind if he had not employed additional men:

1
5/4
3/2
7/4
2
For both questions, we need to employ the notion of "man days." For example, if it takes 7 men working 9 days each to complete a job, then the job takes 63 "man days" (7x9) to complete. So, we can also conclude that if there were only 3 men working on the job, then the same job would take 21 days (63/3) to complete.

Question 1:
Let x be the number of men originally hired.
Since it is not explicitly stated in the question, we must assume that these x men would have completed the job in 9 days (given the ambiguity, I'm pretty sure this is not an official question :-). So, the job will take 9x man days to complete.

If 6 men do not come to work, then there are x-6 men and it takes them 15 days to complete the same job. In other words, the number of man days required is 15(x-6)

We can create the equation 9x = 15(x-6)
When we solve for x, we get x=15.
So, there must have been 15 men originally. (The answer is not provided in the choices)

Question 2:
Determine the total number of man days required to complete the job.
30 men working for 25 days = 750 man days (30x25)
35 men working for 12 days = 420 man days (35x12)
Total number of man days to complete the job = 1170

If the contractor had not hired the additional men it would have taken 1170/30 days for the thirty men to complete the job.

1170/30 = 39, so it would have taken one extra day to complete the job. The answer is A
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion

by maihuna » Tue May 05, 2009 4:38 am
Hi bren,
here we go(where is dumb btw):

A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men , but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The no of men originally employed were:
=========================
Let n = no of men

so 9n = (n-6)*15
so 9n = 15n -90 or 6n = 90 or n=15
Since 6 are abscent work started wit 15-6 = 9 mens.
===========================


A contractor employed 30 men to do a piece of work in 38 days, after 25 days he employed 5 men more and the work was finished one day earlier. how many days he would have been behind if he had not employed additional men:
============================
originally thought : 30*38 = 1140
now: 30*25 + (30+5)*(38-25-1) = 750+35*12 = 750+420 = 1170

so adiitional work = 1170-1140 so yes 30 so yes 1 day for 30 men
Join the discussion

by Brent@GMATPrepNow » Tue May 05, 2009 5:25 am
A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men , but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The no of men originally employed were:
=========================
Let n = no of men

so 9n = (n-6)*15
so 9n = 15n -90 or 6n = 90 or n=15
Since 6 are abscent work started wit 15-6 = 9 mens.
Hmm, it seems that the contractor originally employed 15 men but 6 did not show up. If you want the answer to be 9, perhaps the question should read, "The number of men that showed up for work was "
Brent Hanneson - Creator of GMATPrepNow.com
Image
Join the discussion