A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
Source:prep review book
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
Redeem
Scott Woodbury-Stewart’s private virtual classroom — 400 hours of master-class video lessons for the GMAT Focus Edition.
A can finish 1/5 th of work each day and B can finish 1/10 theaakbari wrote:A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
one more method. If you internalize percentages concept, it will be a very strong tool for you to do these kinds of sums.eaakbari wrote:A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
eaakbari wrote:A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
Bhai,gmatmachoman wrote:eaakbari wrote:A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
SO what if A & B work every third day???
Harsha bhai...plz give me some handy formula!
@eaakbari..eaakbari wrote:The OA is 6.5 days
Thanks guys
Instead of every alternate day, if it asks every third day???harshavardhanc wrote:Bhai,gmatmachoman wrote:eaakbari wrote:A can finish a work in 5 days and B can finish it in 10 days. Let A and B work every alternate day starting with A. In how many days will they finish?
Source:prep review book
SO what if A & B work every third day???
Harsha bhai...plz give me some handy formula!
do you mean : first day - A, second day-B and third day - both ( with this pattern continuing?)
you mean A works on 1st day, then A &B take rest on 2nd day, then B works on 3rd day, then rest, then A......like this??gmatmachoman wrote:
Instead of every alternate day, if it asks every third day???