Start the planMachines X and Y work at their respective constant rates. How many more hours does it take machine Y, working alone, to fill a production order of a certain size than it takes machine X, working alone?
1) Machines X and Y, working together, fill a production order of this size in two-thirds the time that machine X, working alone, does.
2) Machine Y, working alone, fills a production order of this size in twice the time that machine X, working alone, does.
The OA is E