Start the planA. 1/2
B. 3/5
C. 3/4
D. 4/5
E. 7/8
OA D
Source: Veritas Prep
Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.
See classesLearn live with an expert or move at your own pace. Every option includes the complete TTP study system.
Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.
with Josh Braslow, 20+ years in test prep
Self-paced EA prep. Study on your schedule.
with
Complete access from day one. Study on your schedule.
right wrong
Pick an answer to see how members did
Log this miss in the free GMAT error log
Get the error logGet one like this every day: the free 60-day plan
Start the planSince the rate of Hose B (1/4 per hours) is greater than the rate of Hose A (1/6 per hours), part of the half pool filled by Hose B = 1/2 of (6/(6 + 4) = 1/2 of 6/10 = 3/10;BTGmoderatorDC wrote: ↑Sun Mar 01, 2020 6:55 pmTwo hoses (A and B) are filling a pool. Working alone at their individual constant rates Hose A could fill the pool in 6 hours, and Hose B could do it in 4 hours. If the two hoses work together until half the pool is full, and then Hose B finishes the pool alone, what fraction of the pool will have been filled by Hose B?
A. 1/2
B. 3/5
C. 3/4
D. 4/5
E. 7/8
OA D
Source: Veritas Prep
The combined rate of A and B is:BTGmoderatorDC wrote: ↑Sun Mar 01, 2020 6:55 pmTwo hoses (A and B) are filling a pool. Working alone at their individual constant rates Hose A could fill the pool in 6 hours, and Hose B could do it in 4 hours. If the two hoses work together until half the pool is full, and then Hose B finishes the pool alone, what fraction of the pool will have been filled by Hose B?
A. 1/2
B. 3/5
C. 3/4
D. 4/5
E. 7/8
OA D
Source: Veritas Prep