BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
Vote for Target Test Prep, Newsweek Readers’ Choice Awards 2026
NEWSWEEK READERS’ CHOICE 2026

BIG NEWS! Target Test Prep has been nominated, and they’d love your vote!

TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

Vote for TTP
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Total Cost.MGMAT Ques

Expert replies
by rb90 » Fri Sep 10, 2010 9:43 pm
The total cost of producing item X is equal to the sum of item X's fixed cost and variable cost. If the variable cost of producing X decreased by 5% in January, by what percent did the total cost of producing item X change in January?

(1) The fixed cost of producing item X increased by 13% in January.

(2) Before the changes in January, the fixed cost of producing item X was 5 times the variable cost of producing item X.

THE ACTUAL ANSWER IS "C".


( I cant understand why B cant be the answer.Since we know the proportion between the FC and the VC, cant we add them up like : TC= 5x + .95x ; an then find out the percentage difference in the TC? )

PLEASE HELP.
Thank You.
Join the discussion
Source: — Data Sufficiency |

by pradeepkaushal9518 » Sat Sep 11, 2010 1:55 am
cop of X= fixed cost+vari cost

x=fc+vc
vc decersed by 5 % in jan what % change in total cost of X in jan ?

1.fixed cost increased by 13 % in jan

suppose x= 100 +100 in jan vc 5 % decrese and fc incresed by 13 %

x= 113+95=208 so % change is 208-200/200=8*100/200= 4 %

so 1 is suff

2. before change in jan fc=5.vc

suppose x= 120 befeore jan so x= 100+20

in jan vc decersed by 5 % s0 x=100+19=119 so we can calculate the % change so suff

i think answer is D not C
A SMALL TOWN GUY
Join the discussion

by harupit200281 » Sat Sep 11, 2010 10:49 pm
What if the fixed and variable prices are distributed as follows?

100 and 1
1 and 1000

??????
Answer is indeed C
Join the discussion

by gmatmachoman » Sat Sep 11, 2010 11:07 pm
TC = FC +VC
= X+Y

Percent change : 100 * [{X1 +Y1 - (X+Y)}/ (X+Y)]

St1 : {1.13X +0.95 Y - (X+Y)}/(X+Y)

= (0.13X-0.05Y) /(X+Y)

st 2 : X= 5Y

use st1 & st 2

Percent change = 10.75%

Pick C
Join the discussion

by rb90 » Mon Sep 20, 2010 10:36 pm
Dear gmatmachoman
You didnt elaborate on statement 2.If x=5y then,
TC= 5Y+Y=6Y

NEW TC= 5Y + 0.95Y
= 5.95Y

SO % CHANGE = (6Y - 5.95Y)/6Y*100
= 5/6 %

IS THIS CORRECT?