Start the plan(1) Because of production problems, the manufacturer produced only \(600\) tools per day during the first \(5\) days.
(2) Because of production problems, the manufacturer had to produce \(1,500\) tools per day on each of the last \(4\) days in order to meet the schedule.
Answer: E