BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Time when server will be complete

Expert replies
Source: — Problem Solving |

Re: Time when server will be complete

by dtweah » Sat Apr 04, 2009 3:33 pm
Vemuri wrote:Answer with your reasoning.
If 6 men can do a job in 10 hours, they expend 60 man-hour of labor to do the job. If these 6 men ork for anything less than 10 hours, they will only do a fraction of the job. So they begin at 11AM and say they got stopped by the boss at 5:PM. That is 6 hours of work they have completed. Lets see what fraction of the work they have done.

6man * 6 hours/6 man * 10 hours = 36/60 man hours. They still have to do 24man-our of labor. Now between 5 and 6PM, one more person will be joining them, making it 7men, who will only have worked for 1 hour at 6PM. 7man * 1 hr/24man *hour is the fraction of the work these 7 will do. They leave 17 manhour of labor undone (24-7). Then the boss adds another man between 6PM and 7PM making them now 8men trying to do 17 man hour in one hour. 8/17. At 7 PM he stops them and say (boys you are one group of lazybones. They have 17-8 = 9 man hours to go between 7 and 8PM. He sounds the order again and adds one last man making them 9 men doing 9 man-hour of labor: 9/9 and at 8PM they do complete 60manhour/60man hour of job. He dismisses them without pay. Cruel boss.