If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.
See classesLearn live with an expert or move at your own pace. Every option includes the complete TTP study system.
Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.
with Josh Braslow, 20+ years in test prep
Self-paced EA prep. Study on your schedule.
with
Complete access from day one. Study on your schedule.
6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
Anurag@Gurome wrote:6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
1 worker can build 4 cars in 2*6 = 12 days
1 worker can build 1 car in 12/4 = 3 days
1 worker can build 6 cars in 3*6 = 18 days
8 workers can build 6 cars in 18/8 = [spoiler]9/4[/spoiler] days
The correct answer is B.
Thank you for this Anurag....
I was struggling with different time consuming, now i am ok with ur explanation