If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
Redeem
Scott Woodbury-Stewart’s private virtual classroom — 400 hours of master-class video lessons for the GMAT Focus Edition.
6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
Anurag@Gurome wrote:6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
1 worker can build 4 cars in 2*6 = 12 days
1 worker can build 1 car in 12/4 = 3 days
1 worker can build 6 cars in 3*6 = 18 days
8 workers can build 6 cars in 18/8 = [spoiler]9/4[/spoiler] days
The correct answer is B.
Thank you for this Anurag....
I was struggling with different time consuming, now i am ok with ur explanation