BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

There are 4 machines with the same work rate. If it took k

Expert replies
by Max@Math Revolution » Thu Mar 01, 2018 2:40 am
[GMAT math practice question]

There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?

A. 4
B. 5
C. 6
D. 7
E. 8
Join the discussion
Source: — Problem Solving |

by mbawisdom » Thu Mar 01, 2018 6:20 am
Max@Math Revolution wrote:[GMAT math practice question]

There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?

A. 4
B. 5
C. 6
D. 7
E. 8
Total machine working hours will be the same for 3 machines and 4 machines.

Total machine hours with 3 machines = 3k
Total machine hours with 4 machines = 4(k-2)

3k = 4(k-2)
3k = 4k - 8
k = 8

Answer = (E) 8
Join the discussion

by Max@Math Revolution » Sun Mar 04, 2018 6:17 pm
=>

Work Amount = Number of machines * Work Rate * Time
If r is the machine's work rate, we have 3rk = 4r(k-2) or 3k = 4k -8.
Thus k = 8.

Therefore, E is the answer.

Answer: E
Join the discussion

by Scott@TargetTestPrep » Mon Jun 10, 2019 6:17 pm
Max@Math Revolution wrote:[GMAT math practice question]

There are 4 machines with the same work rate. If it took k hours for 3 machines to work and did k-2 hours for 4 machines when working together, what is the value of k?

A. 4
B. 5
C. 6
D. 7
E. 8
Let the rate of each machine be r. We can create the equation:

(3r)k = (4r)(k - 2)

3k = 4k - 8

8 = k

Answer: E