BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Six computers, each working at the same constant rate . . .

Expert replies
by VJesus12 » Sat Jan 06, 2018 4:02 am
Six computers, each working at the same constant rate, together can process a certain amount of data in 15 days. How many additional computers, each working at the same constant rate, will be needed to process the same amount of data in 10 days?

(A) 3
(B) 5
(C) 6
(D) 9
(E) 12

The OA is the option A.

What is the equation I should use? How can I know how much data process each computer? Experts, can you help me? Thanks in advanced.
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Sat Jan 06, 2018 4:39 am
VJesus12 wrote:Six computers, each working at the same constant rate, together can process a certain amount of data in 15 days. How many additional computers, each working at the same constant rate, will be needed to process the same amount of data in 10 days?

(A) 3
(B) 5
(C) 6
(D) 9
(E) 12
Use the following formula:
(workers)(time) = (workers)(time).

Since 6 computers take 15 days, we must determine how many computers are required to complete the job in 10 days, we get:
(6 computers)(15 days) = (x computers)(10 days)
6*15 = 10x
90 = 10x
x = 9.

Since 9 computers are required, the number of computers that must be added to the 6 original computers = 3.

The correct answer is A.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by [email protected] » Sat Jan 06, 2018 11:32 am
Hi VJesus12,

We're told that 6 computers, each working at the same constant rate, together can process a certain amount of data in 15 days. We're asked how many ADDITIONAL computers, each working at the same constant rate, would be needed to process the SAME amount of data in 10 days.

In these types of 'work' questions, it often helps to start by calculating the total amount of unit-work that is needed to complete a task. Here, we have 6 computers that each work for 15 days to complete a task. This means:

(6 computers)(15 days of work each) = 90 computer-days of work needed to complete a task.

We're asked how many computers ADDITIONAL computers would be needed to complete the task in 10 days...

(X computers)(10 days of work each) = 90 computer-days of work needed
X = 90/10 = 9 total computers needed to complete the task in 10 days.

Since we already have 6 computers, 3 ADDITIONAL computers are needed.

Final Answer: A

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by Scott@TargetTestPrep » Sun Aug 11, 2019 6:34 pm
VJesus12 wrote:Six computers, each working at the same constant rate, together can process a certain amount of data in 15 days. How many additional computers, each working at the same constant rate, will be needed to process the same amount of data in 10 days?

(A) 3
(B) 5
(C) 6
(D) 9
(E) 12

The OA is the option A.
If 6 computers can process the data in 15 days, one computer can process the same data in 15 x 6 = 90 days.

To have the number of days reduced by a factor of 1/9 (i.e from 90 days to 10 days), we need to increase the number of computers by a factor of 9 (i.e. from 1 computer to 9 computers). Since we already have 6 computers at hand, we need 9 - 6 = 3 additional computers.

Alternate Solution:

The total number of computer-days required for this task is 6 x 15 = 90 computer-days.

The task could be accomplished by 1 computer in 90 days (since 1 x 90 = 90 computer-days), or by 2 computers in 45 days (since 2 x 45 = 90 computer-days), etc.

In this problem, we want the 90 computer-hours to be accomplished in 10 days, so we need 90/10 = 9 computers, which is 3 more than what we currently have.

Answer: A

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion