BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Scheduling problem:

Expert replies
by \'manpreet singh » Sun Jul 01, 2012 9:48 pm
Q.1)How many days after the purchase of Product X does its standard warranty expire? (1997 is not a leap year.)
(1) When Mark purchased Product X in January 1997, the warranty did not
expire until March 1997.
(2) When Santos purchased Product X in May 1997, the warranty expired in
May 1997.

kindly help me with this question(I don't understand why have they mentioned leap year thing in question)
Join the discussion
Source: — Data Sufficiency |

by Anurag@Gurome » Mon Jul 02, 2012 12:16 am
'manpreet singh wrote:Q.1)How many days after the purchase of Product X does its standard warranty expire? (1997 is not a leap year.)

(1) When Mark purchased Product X in January 1997, the warranty did not expire until March 1997.
(2) When Santos purchased Product X in May 1997, the warranty expired in May 1997.
Statement 1: Maximum possible validity of X is from 1st January to 31st March = (31 + 28 + 31) = 90 days
Minimum possible validity of X is from 31st January to 1st March = (1 + 28 + 1) = 30 days

Hence, the answer could be anything between 30 days and 90 days, both inclusive.

Not sufficient

Statement 2: Maximum possible validity of X is from 1st May to 31st March = 31 days
Minimum possible validity of X is from 1st May to 1st May = 1 day

Hence, the answer could be anything between 1 day and 31 days, both inclusive.

Not sufficient

1 & 2 Together: The answer could be 30 or 31.

Not sufficient

The correct answer is E.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/
Join the discussion

by \'manpreet singh » Mon Jul 02, 2012 8:33 pm
Thanks for the quick response.
I figured the leap year thing, if it would have been a leap year then
minimum for statement1 would be 31 days.
and combining both the statements.

The answer would be C ( Both statements together sufficient) :D :)
Join the discussion

by bubbliiiiiiii » Tue Jul 03, 2012 5:55 am
Hi Manpreet,

The leap year thing is given so that the number of days can be accurately counted while working on options A and B. This is so because, option A has February included and option B does not.

I echo with Anurag and IMO, answer should be E.

Could you please elaborate your reason for choosing C and post OA?
Regards,

Pranay
Join the discussion

by \'manpreet singh » Wed Jul 04, 2012 12:01 pm
bubbliiiiiiii wrote:Hi Manpreet,

The leap year thing is given so that the number of days can be accurately counted while working on options A and B. This is so because, option A has February included and option B does not.

I echo with Anurag and IMO, answer should be E.

Could you please elaborate your reason for choosing C and post OA?
The answer to my question is indeed E as explained by anurag.

But the answer would have been C if it had been a leap year, that's what I was trying to explain in the above post so please don't confuse.
Join the discussion

by bubbliiiiiiii » Thu Jul 05, 2012 12:42 am
My mistake! :(
Regards,

Pranay
Join the discussion

by nevagivup » Wed Jul 31, 2013 10:02 pm
Hi Anurag,

i have a doubt in this ..plz correct me

In Statement 1: Maximum validity is from 1st January to 31st March
Minimum validity is from 31st January to 1st March ( WE ARE SURE that 31st march as well as 1st march is not an expiry date HERE)

= (31 + 28 + 31) = 90 days
= (1 + 28 + 1) = 30 days

In Statement 2: (2) When Santos purchased Product X in May 1997, the warranty expired in May 1997.

Maximum possible validity of X is from 1st May to 31st may = 30 days( here we ARE ASSUMING THAT 31st is an expiry date according to the question so we cnnt include 31st day )
Minimum possible validity of X is from 1st May to 2nd May = 1 day
Join the discussion

by Matt@VeritasPrep » Thu Aug 01, 2013 9:47 am
nevagivup wrote:Hi Anurag,

i have a doubt in this ..plz correct me

In Statement 1: Maximum validity is from 1st January to 31st March
Minimum validity is from 31st January to 1st March ( WE ARE SURE that 31st march as well as 1st march is not an expiry date HERE)

= (31 + 28 + 31) = 90 days
= (1 + 28 + 1) = 30 days

In Statement 2: (2) When Santos purchased Product X in May 1997, the warranty expired in May 1997.

Maximum possible validity of X is from 1st May to 31st may = 30 days( here we ARE ASSUMING THAT 31st is an expiry date according to the question so we cnnt include 31st day )
Minimum possible validity of X is from 1st May to 2nd May = 1 day
I'd agree with your interpretation of the calendar. If I buy a warranty on August 1st, and it lasts till August 2nd, that is a 24 hour, or 1 day warranty (not a 2 day warranty, per Anurag's interpretation, at least IMO - I guess it depends on the terms of the contract).

If you accept this interpretation, the warranty could be either 29 days or 30 days, given the two statements. (January 31st -> March 1st = 29 days, January 31st -> March 2nd = 30 days; March 1st -> March 30th = 29 days, March 1st -> March 31st = 30 days.)

So the answer is still E.