Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Running at their respective constant rates,Machine x takes 2

Expert replies
by mitzwillrockgmat » Sun Jun 13, 2010 6:27 am
Running at their respective constant rates, Machine x takes 2 days longer to produce w widgets than Machine Y. At these rates, if the two machines together produce 5/4w widgets in 3 days, how many days would it take machine X alone to produce 2w widgets?

A)4
B)6
C)8
D)10
E)12

I'm having trouble solving this algebraicly (?). Pls help!

This is what I did:

so given info above : rate for x is w/ [d+2] & rate for y is w/d.

working together they can make 5/[4w] widgets in 3 days so since, rate=work/time ...combined rate= [5/(4w)]/3 = 5/12w

So we can solve for d : w/[d +2] + w/d = 5/12w

5/12w = dw +w[d+2] / d[d +2]
= dw +dw +2w / d^2 +2d
= 2wd + 2w / d^2 +2d
5wd^2 + 10wd = 24dw + 24w
5wd^2 + 10wd - 24dw - 24w = 0
5wd^2 - 14wd - 24w = 0

divide the entire eq by w , we get: 5d^2 - 14d - 24 = 0

Now what do i do??????

it would be very time consuming for me to find two no.s that add upto 14/5 and equal 24/5 when multiplied.

I tried the quadratic eq formula & i was able to get d=4 though.

so if d=4, then d+2=6. so it takes x 6 days to make w widgets & 12 days to make 2w widgets.

BUT STILL i want to know how i can solve the above algebraicly! or is this the only way?!
Join the discussion
Source: — Problem Solving |

by albatross86 » Sun Jun 13, 2010 6:41 am
You reached here fine:

=> 5d^2 - 14d - 24 = 0

Look at it this way : Find 2 numbers a and b such that a + b = - 14 and a * b = -120
a and b can thus be -20 and 6

=> 5d^2 - 20d + 6d - 24 = 0
=> 5d(d - 4) + 6(d - 4) = 0

Therefore d = 4
Join the discussion

by mitzwillrockgmat » Sun Jun 13, 2010 6:46 am
albatross86 wrote:You reached here fine:

=> 5d^2 - 14d - 24 = 0

Look at it this way : Find 2 numbers a and b such that a + b = - 14 and a * b = -120
a and b can thus be -20 and 6

=> 5d^2 - 20d + 6d - 24 = 0
=> 5d(d - 4) + 6(d - 4) = 0

Therefore d = 4
That's exactly what i was looking for, thank you!!