BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

rates

Expert replies
by yvonne12 » Sun Mar 04, 2007 12:20 pm
I want to know if I did this right.

six machines working at a constant rate together can complete a certain job in 12 days. How many additional machines each working at the same constant rate will be needed to complete the job in 8 days?

ans 3
6/x = x/8 cross multiply and get 3

is this correct?
Join the discussion
Source: — Problem Solving |

by jayhawk2001 » Sun Mar 04, 2007 6:03 pm
Use the standard rate-formula to solve this

6 machines complete the job in 12 days, so
6 * 1/x = 1/12, so x = 72

n additional machines complete the job in 8 days
(n+6) * 1/72 = 1/8

So, n = 3
Join the discussion

by Scott@TargetTestPrep » Mon Jun 25, 2018 11:16 am
yvonne12 wrote:
six machines working at a constant rate together can complete a certain job in 12 days. How many additional machines each working at the same constant rate will be needed to complete the job in 8 days?
We are given that six machines, each working at the same constant rate, together can complete a certain job in 12 days. Since rate = work/time and if we consider work as 1, the rate of the six machines is 1/12.

We need to determine how many additional machines, each working at the same constant rate, will be needed to complete the same job in 8 days. In other words we need to determine how many additional machines are needed to work at a rate of 1/8. Since each machine works at the same constant rate, we can use a proportion to first determine the number of machines needed to work at the rate of 1/8.

Our proportion is as follows: 6 machines is to a rate of 1/12 as x machines is to a rate of 1/8.

6/(1/12) = x/(1/8)

72 = 8x

x = 9

So we need 9 - 6 = 3 more machines.

Answer: 3