Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Rates and Work

Expert replies
by snapplesf » Fri Mar 23, 2007 11:03 am
source - GMATPrep
--------------------------------------------

6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8



see answer below









Ans = 3

Is there a technique to this problem type ? Applied the standard RT=W principles, but lost on this one..

------------------------------------------------------------------
Join the discussion
Source: — Problem Solving |

by jayhawk2001 » Fri Mar 23, 2007 6:00 pm
Let x be the time it takes for 1 machine to complete the job

6 * 1/x = 1/12
x = 72 days

n machines can complete the job in 8 days, so
n * 1/72 = 1/8
n = 9

Additional machines required = 9-6 = 3 days
Join the discussion

by snapplesf » Sat Mar 24, 2007 9:12 am
thanks jayhawk2001 !
Join the discussion

by Cybermusings » Tue Mar 27, 2007 5:07 am
6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8

This one is easy -

6 Machines - 1 Work - 12 Days

1 Machine - 1 Work - 12 * 6 Days

x Machines - 1 Work - 12 * 6 / x Days

12 * 6 / x = 8

Therefore x = 9

Thus 9 - 6 = 3 additional machines are needed

Hope this helps
Join the discussion

by Scott@TargetTestPrep » Wed Jun 20, 2018 4:30 pm
snapplesf wrote: --------------------------------------------

6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8
We are given that six machines, each working at the same constant rate, together can complete a certain job in 12 days. Since rate = work/time, and if we consider work as 1, the rate of the six machines is 1/12.

We need to determine how many additional machines each working at the same constant rate will be needed to complete the same job in 8 days. In other words, we need to determine how many additional machines are needed to work at a rate of 1/8. Since each machine works at the same constant rate, we can use a proportion to first determine the number of machines needed to work at the rate of 1/8.

Our proportion is as follows: 6 machines is to a rate of 1/12 as x machines is to a rate of 1/8.

6/(1/12) = x/(1/8)

72 = 8x

x = 9

So, we need 9 – 6 = 3 more machines.

Answer: B