BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATBootcamp Starts Sep 28
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE BOOTCAMP

Live Online Bootcamp Class with Top GMAT Expert Chris Peckover

15 live classes from Sep 28, 2026

Schedule
Mon to Fri · 7:00 to 10:00 PM ET
Included
Live classes + 6 months of TTP OnDemand
  • Boost your GMAT score in less than one month in a live online class
  • 6 months access to TTP OnDemand video courses included
View bootcamp & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rate problem

Expert replies
by chiangka » Sat Apr 16, 2011 12:54 pm
Anybody know a good strategy to solve the following:

Pumps A,B, and C operate at their respective constant rates. Pumps A and B, operating simultaneously, can fill a certain tank in 6/5 hours; pumps A and C, operating simultaneously, can fill the tank in 3/2 hours; pumps B and C, operating simultaneously, can fill the tank in 2 hours. How many hours does it take pumps A, B, and C, operating simultaneously to fill the tank?

A) 1/3
B) 1/2
C) 2/3
D) 5/6
E) 1

Answer: e
Join the discussion
Source: — Problem Solving |

by havok » Sat Apr 16, 2011 1:02 pm
So the basic "rate" equation is:

1/A + 1/B = 1/T

You are given 3 scenarios:
1/A + 1/B = 1 / (6/5) = 5/6
1/B + 1/C = 1 / (3/2) = 2/3
1/A + 1/C = 1 / 2 = 1/2

Once you've set this up, simply use your algebra skills to determine that:
A = 2, B = 3, and C = 6

Therefore, 1/A + 1/B + 1/C = 1/T
or
1/2 + 1/3 + 1/6 = 1 / T
T = 1. E.
Join the discussion

by manpsingh87 » Sat Apr 16, 2011 8:42 pm
havok wrote:So the basic "rate" equation is:

1/A + 1/B = 1/T

You are given 3 scenarios:
1/A + 1/B = 1 / (6/5) = 5/6
1/B + 1/C = 1 / (3/2) = 2/3
1/A + 1/C = 1 / 2 = 1/2

Once you've set this up, simply use your algebra skills to determine that:
A = 2, B = 3, and C = 6
there is no need to determine the value of A,B and C, simply add three equations to get the desired result...!!!
O Excellence... my search for you is on... you can be far.. but not beyond my reach!
Join the discussion

by Geva@EconomistGMAT » Sat Apr 16, 2011 11:06 pm
there is no need to determine the value of A,B and C, simply add three equations to get the desired result...!!!
This is fine if you are comfortable with the concept that if A,B and C are the rate, then 1/A, a/b and 1/C are the time it takes them to fill one tank, and 2/A, 2/B and 2/C are "twice the time" - which is true, but not an easy point to conceptualize automatically. If you are fine with this concept, and are also comfortable working with fractions so that 5/6 + 2/3 + 1/2 is a breeze, then the following post is not meant for you - keep doing what you do.

For the rest of the world:
when the work is not defined (a pool, a job, a wall, a tank), plug in a good number for the work. A good number will be divisible numbers in the question: In this case, we have 6/5, 3/2 and 2/1, so we'll use 6*5*2 = 60 for the work. The actual number does not really matter - the goal is to use a large nubmber for the work, so that the rate is given in real integers, rather than the fraction 1/A. To aid in conceptualizing the problem, it helps to think of "units": 60 liters in the tank, for example.

Use the plugged in work to find the rate. So
A and B can do 60 liters in 6/5 hours, so their rate is 60 / 6/5 = 60*5/6 = 50 li/hr.
A+C = 60/3/2 = 60*2/3 = 20*2 = 40 li/hr.
B+C = 60/2=30 li/hr.

Add all three equations together:

A+B+A+C+B+C = 50+40+30 = 120 li/hr.
2A+2B+2C = 120 li/hr /:2
A+B+C = 60 li/hr.

so A, B, and C will take 1 hour to finish the 60 liter tank together.
Geva
Senior Instructor
Master GMAT
1-888-780-GMAT
https://www.mastergmat.com
Join the discussion

by Ryandmitri » Sat Apr 16, 2011 11:51 pm
Just to get an indication...what difficulty rating would you give to this problem?
Join the discussion

by Geva@EconomistGMAT » Sat Apr 16, 2011 11:56 pm
Ryandmitri wrote:Just to get an indication...what difficulty rating would you give to this problem?
It ain't easy, that's for sure. I'd say a 47+.
Geva
Senior Instructor
Master GMAT
1-888-780-GMAT
https://www.mastergmat.com
Join the discussion

by manpsingh87 » Sun Apr 17, 2011 12:48 am
Geva@MasterGMAT wrote:
there is no need to determine the value of A,B and C, simply add three equations to get the desired result...!!!
This is fine if you are comfortable with the concept that if A,B and C are the rate, then 1/A, a/b and 1/C are the time it takes them to fill one tank, and 2/A, 2/B and 2/C are "twice the time" - which is true, but not an easy point to conceptualize automatically. If you are fine with this concept, and are also comfortable working with fractions so that 5/6 + 2/3 + 1/2 is a breeze, then the following post is not meant for you - keep doing what you do.

For the rest of the world:
when the work is not defined (a pool, a job, a wall, a tank), plug in a good number for the work. A good number will be divisible numbers in the question: In this case, we have 6/5, 3/2 and 2/1, so we'll use 6*5*2 = 60 for the work. The actual number does not really matter - the goal is to use a large nubmber for the work, so that the rate is given in real integers, rather than the fraction 1/A. To aid in conceptualizing the problem, it helps to think of "units": 60 liters in the tank, for example.

Use the plugged in work to find the rate. So
A and B can do 60 liters in 6/5 hours, so their rate is 60 / 6/5 = 60*5/6 = 50 li/hr.
A+C = 60/3/2 = 60*2/3 = 20*2 = 40 li/hr.
B+C = 60/2=30 li/hr.

Add all three equations together:

A+B+A+C+B+C = 50+40+30 = 120 li/hr.
2A+2B+2C = 120 li/hr /:2
A+B+C = 60 li/hr.

so A, B, and C will take 1 hour to finish the 60 liter tank together.
hi geva, thanks a lot for sharing an alternative method, its always good to learn new things...!!!