BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rate problem

Expert replies
by anniev2 » Fri Mar 13, 2009 10:32 am
From OG Math Review Section: If Machine X can produce 1,000 bolts in 4 hours and machine Y can produce 1,000 bolts in 5 hours, in how many hours can machines X and Y, working together at these constant rates, produce 1,000 bolts?

1/4 = 1/5 = 1/h
h = 2 2/9

Let's say, Machine X could produce 2,500 bolts in 6 hours. How Would the equation be set up?
Join the discussion
Source: — Problem Solving |

by sureshbala » Fri Mar 13, 2009 10:48 am
anniev2 wrote:From OG Math Review Section: If Machine X can produce 1,000 bolts in 4 hours and machine Y can produce 1,000 bolts in 5 hours, in how many hours can machines X and Y, working together at these constant rates, produce 1,000 bolts?

1/4 + 1/5 = 1/h
h = 2 2/9

Let's say, Machine X could produce 2,500 bolts in 6 hours. How Would the equation be set up?
As mentioned by you X produces 2,500 bolts in 6 hrs, i.e 5000 bolts in 12 hrs.

Similarly, Y produces 5000 bolts in 25 hrs.

So X and Y working together can produce 5000 bolts in 300/37 hrs.

Hence X and Y working together can produce 1000 bolts in 300/(37x5) = 60/37 hrs = 1 23/37 hrs
Join the discussion

by anniev2 » Fri Mar 13, 2009 10:52 am
Thank you! Rate problems are a weakness of mine and this helps me understand the strategy better.

Your logic was to make the amount of work done by both machines the same and then use the standard work/rate formula. Then you divided the result of the equation appropriately to provide the amoutn of work asked for in the question.