BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rate Problem - Machine X and Y HELP

Expert replies
by gmatpup » Sun Nov 06, 2011 7:17 am
In the GMAT quant review (2nd ed) I came across a question that I just cannot seem to figure out. Please help!!

173. Running at their respective constant rates, Machine X takes 2 days longer to produce w widgets than Machine Y. At these rates, if the two machines together produce 5/4w widgets in 3 days, how many days would it take Machine X alone to produce 2w widgets?

A. 4
B. 6
C. 8.
D. 10
E. 12

The answer is E but I just don't see how!

Thanks so much for any explanation :)
Join the discussion
Source: — Problem Solving |

by GmatMathPro » Sun Nov 06, 2011 8:01 am
First, note that for something like this, the answer should be true regardless of the value of w. Hence, we can choose any non-negative value for w. Let's say w=1. Let's say machine Y takes y days to make w widgets. This would mean that machine X takes y+2 days to make w widgets. Substituting in 1 for w, we can say that machine Y makes 1 widget every y days, and machine X makes 1 widget every y+2 days. In work-rate-time problems like these, you can find a person or machine's rate by dividing the number of things done by the amount of time it takes them, so we can say machine Y works at a rate of 1/y widgets per day and machine X works at a rate of 1/(y+2) widgets per day. Therefore, in 3 days, machine Y makes 3/y widgets, and machine X makes 3/(y+2) widgets. Combined, we are told that they can make 5w/4 widgets in 3 days, so we can write: 3/y+3/(y+2)=5/4. Multiply both sides of the equation by the LCD, 4y(y+2) in order to cancel out the fractions: 3(4)(y+2)+3(4)(y)=5y(y+2). Distributing and simplifying, this equation becomes 5y^2-14y-24=0. This factors as (5y+6)(y-4)=0. y must be positive, so it must be the case that y=4.

So, how long does it take machine X to make 2 widgets? if y=4, it makes 1 widget in 6 days, so it can make 2 widgets in 12 days.

Ans: E
Pete Ackley
GMAT Math Pro
Free Online Tutoring Trial
Join the discussion

by GMATGuruNY » Mon Nov 07, 2011 9:42 am
gmatpup wrote:In the GMAT quant review (2nd ed) I came across a question that I just cannot seem to figure out. Please help!!

173. Running at their respective constant rates, Machine X takes 2 days longer to produce w widgets than Machine Y. At these rates, if the two machines together produce 5/4w widgets in 3 days, how many days would it take Machine X alone to produce 2w widgets?

A. 4
B. 6
C. 8.
D. 10
E. 12

The answer is E but I just don't see how!

Thanks so much for any explanation :)
I posted an alternate approach here:

https://www.beatthegmat.com/how-many-day ... 11577.html
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.