Rate Problem from GMAT Prep

This topic has expert replies
Master | Next Rank: 500 Posts
Posts: 215
Joined: Mon Apr 21, 2008 8:07 am

Rate Problem from GMAT Prep

by rosh26 » Tue Jun 10, 2008 3:13 pm
Each of 10 machines works at a constant rate to do a certain job. The amount of time needed by the 10 machines working together is 16 hours.

How many hours would be needed if only 8 machines, working together, were used to complete the job?

Answer is 20

How did they get this answer???