Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

rate and work

Expert replies
by gmatnmein2010 » Mon Feb 08, 2010 5:35 am
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Join the discussion
Source: — Problem Solving |

by harsh.champ » Mon Feb 08, 2010 6:01 am
gmatnmein2010 wrote:A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Let an imaginary unit be 110 works.
1 man will complete the 110works in 1100 days.Hence, in 1 day only 0.1work
Till day 60 work done = 60works.
Now,50 works left.
6 more ppl hired.Hence,16 man crew so works done in 1 day = 16x0.1 = 1.6works
Hence,days required = 50/1.6=31.25 which is 32.
so,92 days .
hence [spoiler]8(100-92) E.[/spoiler]
It takes time and effort to explain, so if my comment helped you please press Thanks button :)



Just because something is hard doesn't mean you shouldn't try,it means you should just try harder.

"Keep Walking" - Johnny Walker :P
Join the discussion

by thephoenix » Mon Feb 08, 2010 6:19 am
the job was finish by 10 people 110 days.
nowon the 61-st day, after 5 days of rain --> 5 days was rain,
--->55 days they worked ---> they completed 55/110 =1/2 of the job
1/2 is left =55 days of work for 10 people

Now 6 more people was hired -->
10 people in 1 day does sme workand
16 people in 1 day does =16/10 of the same work
hence speed of construction increased by 1.6,
now days needed to finish 55/1.6=34.375,
BUT after they were hired job was done in 100-60=40 days -->
--->approx 5-6 days rained.
They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100 in(40) days.
hence day rain=5 days
HTH
Join the discussion