BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

rate and work

Expert replies
by gmatnmein2010 » Mon Feb 08, 2010 5:35 am
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Join the discussion
Source: — Problem Solving |

by harsh.champ » Mon Feb 08, 2010 6:01 am
gmatnmein2010 wrote:A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Let an imaginary unit be 110 works.
1 man will complete the 110works in 1100 days.Hence, in 1 day only 0.1work
Till day 60 work done = 60works.
Now,50 works left.
6 more ppl hired.Hence,16 man crew so works done in 1 day = 16x0.1 = 1.6works
Hence,days required = 50/1.6=31.25 which is 32.
so,92 days .
hence [spoiler]8(100-92) E.[/spoiler]
It takes time and effort to explain, so if my comment helped you please press Thanks button :)



Just because something is hard doesn't mean you shouldn't try,it means you should just try harder.

"Keep Walking" - Johnny Walker :P
Join the discussion

by thephoenix » Mon Feb 08, 2010 6:19 am
the job was finish by 10 people 110 days.
nowon the 61-st day, after 5 days of rain --> 5 days was rain,
--->55 days they worked ---> they completed 55/110 =1/2 of the job
1/2 is left =55 days of work for 10 people

Now 6 more people was hired -->
10 people in 1 day does sme workand
16 people in 1 day does =16/10 of the same work
hence speed of construction increased by 1.6,
now days needed to finish 55/1.6=34.375,
BUT after they were hired job was done in 100-60=40 days -->
--->approx 5-6 days rained.
They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100 in(40) days.
hence day rain=5 days
HTH