BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rainy day

Expert replies
by ritula » Mon Sep 22, 2008 12:19 am
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
4
5
6
7
8
Philosophers have interpreted world in various ways, the point is to change it!
Join the discussion
Source: — Problem Solving |

Re: Rainy day

by tendays2go » Mon Sep 22, 2008 6:26 am
ritula wrote:A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
4
5
6
7
8

is OA= 5?
My logic:

5 days before 61st day, it was raining so work had been done for 55 days i.e. half of the work done.
now, 55*10 = 550 man-days of work still left
Now, contractor hires 6 more men, making it a total of 16 and work is over in next 40 days. but, 550/16 = 34.4 (approx.) i.e. work should have been over in 95 days itself.
hence 5 more days account for rain.
Join the discussion

by stop@800 » Mon Sep 22, 2008 6:47 am
I also think its 5 days.

whats the OA?

actually few efforts are left and this is making me worry about my answers.

Question says:
If the job was done in 100 days
and no
If the job was done on 100th day
Join the discussion

OA

by ritula » Mon Sep 22, 2008 9:47 pm
yes ans is 5 indeed.
@tendays2go
very nice explanation.