Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Rainy day

Expert replies
by ritula » Mon Sep 22, 2008 12:19 am
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
4
5
6
7
8
Philosophers have interpreted world in various ways, the point is to change it!
Join the discussion
Source: — Problem Solving |

Re: Rainy day

by tendays2go » Mon Sep 22, 2008 6:26 am
ritula wrote:A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?
4
5
6
7
8

is OA= 5?
My logic:

5 days before 61st day, it was raining so work had been done for 55 days i.e. half of the work done.
now, 55*10 = 550 man-days of work still left
Now, contractor hires 6 more men, making it a total of 16 and work is over in next 40 days. but, 550/16 = 34.4 (approx.) i.e. work should have been over in 95 days itself.
hence 5 more days account for rain.
Join the discussion

by stop@800 » Mon Sep 22, 2008 6:47 am
I also think its 5 days.

whats the OA?

actually few efforts are left and this is making me worry about my answers.

Question says:
If the job was done in 100 days
and no
If the job was done on 100th day
Join the discussion

OA

by ritula » Mon Sep 22, 2008 9:47 pm
yes ans is 5 indeed.
@tendays2go
very nice explanation.
Philosophers have interpreted world in various ways, the point is to change it!