BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

PS : Pumps A,B,C

Expert replies
by Xbond » Sat Dec 12, 2009 9:24 am
Hi there,

Could help me to understand why the right answer of this PS is E. I pick B but I didn't find why it is E
A complete explanation is welcome.

Pumps A, B, and C operate at their respective constant rates. Pumps A and B, operating simultaneously, can fill a certain tank in 6/5 hours; pumps A and C, operating simultaneously, can fill the tank in 3/2 hours; and pumps B and C, operating
simultaneously, can fill the tank in 2 hours. How many hours does it take pumps A, B, and C, operating simultaneously, to fill the tank ?

A) 1/3
B) 1/2
C) 2/3
D) 5/6
E) 1
Join the discussion
Source: — Problem Solving |

by Testluv » Sat Dec 12, 2009 10:18 am
Xbond wrote:Hi there,

Could help me to understand why the right answer of this PS is E. I pick B but I didn't find why it is E
A complete explanation is welcome.

Pumps A, B, and C operate at their respective constant rates. Pumps A and B, operating simultaneously, can fill a certain tank in 6/5 hours; pumps A and C, operating simultaneously, can fill the tank in 3/2 hours; and pumps B and C, operating
simultaneously, can fill the tank in 2 hours. How many hours does it take pumps A, B, and C, operating simultaneously, to fill the tank ?

A) 1/3
B) 1/2
C) 2/3
D) 5/6
E) 1
Rate and time are always inversely related:

AB's rate is 6/5, so in 1 hour, AB will do 5/6 of the job.
AC's rate is 3/2, so in 1 hour, AC will do 2/3 of the job.
BC's rate is 2, so in 1 hour, BC will do 1/2 of the job.

Let the number of units in the total job be a number that is a multiple of 6, 3, and 2; let's say there are 18 units in the total job.

Then, in one hour:

AB will complete 5/6*18 = 15 units;
AC will complete 2/3*18 = 12 units;
BC will complete 1/2*18 = 9 units.

Summing up:
2 As, 2 Bs, and 2Cs complete 36 units.
So, in one hour, 2 of each of the pumps will complete two jobs. Therefore, it will take 1 of each of the pumps 1 hour to complete the job.
Kaplan Teacher in Toronto
Join the discussion

by Xbond » Mon Dec 14, 2009 12:11 pm
many thks
Join the discussion

by batbond007 » Mon Dec 14, 2009 12:53 pm
Other way

1/Total time = 1/A + 1/B + 1/C + ... + 1/N

1/time for 2A + 2B + 2C = 5/6 + 2/3 + 1/2 = 2 hrs

Hence time for 2A + 2B + 2C = 1/2 hrs

Hence time for A + B + C = 1 hr.