Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

PS problem! please help

Expert replies
by dqure040 » Thu Oct 22, 2015 7:50 am
At a loading dock, each worker on the night crew loaded 3/4 as many boxes as each worker on the day crew. If the night crew has 4/5 as many workers as the day crew, what fraction of all the boxes loaded by the 2 crews did the day crew load?
a) 1/2, b) 2/5, C) 3/5 d) 9/5 E) 5/8

I'm having a hard time visualizing this question. If N=night crew and D=day crew, i understand N=3/4D, but then I don't follow
Join the discussion
Source: — Problem Solving |

by DavidG@VeritasPrep » Thu Oct 22, 2015 8:06 am
dqure040 wrote:At a loading dock, each worker on the night crew loaded 3/4 as many boxes as each worker on the day crew. If the night crew has 4/5 as many workers as the day crew, what fraction of all the boxes loaded by the 2 crews did the day crew load?
a) 1/2, b) 2/5, C) 3/5 d) 9/5 E) 5/8

I'm having a hard time visualizing this question. If N=night crew and D=day crew, i understand N=3/4D, but then I don't follow
Pick some simple numbers to make the problem concrete. Say, each worker on the night crew loaded 3 boxes and each worker on the day crew loaded 4 boxes. (So we have our 3/4 ratio.)

And say we have have 4 night crew workers and 5 day crew workers, to give us our 4/5 ratio.

If 4 night crew works load 3 boxes each, they load a total of 3*4 = 12 boxes.
If 5 day crew works, load 4 boxes each, the load a total of 5*4 = 20 boxes.
The total boxes loaded = 12 + 20 = 32.

The day crew loaded 20 of 32 boxes or 20/32 = 5/8.
Veritas Prep | GMAT Instructor

Veritas Prep Reviews
Save $100 off any live Veritas Prep GMAT Course
Join the discussion

by [email protected] » Thu Oct 22, 2015 10:04 am
HI dqure040,

TESTing VALUES (the approach that David used) is a fairly easy way to work through this question. If you want to use an Algebraic approach, then that's fine, but you have to be very careful about what your variables represent. I'm going to give you some help in setting up the 'terms' so that you can reattempt the Algebra on your own...

The number of night workers is related to the number of day workers, but NOT the way that you wrote your equation.

IF...
N = number of night workers
D = number of day workers

N = (4/5)D

Next, you have to create a variable and an equation for the number of boxes loaded per employee.

B = number of boxes loaded

B = number loaded per day worker
(3/4)B = number loaded per night worker

Using these equations and ideas, what would you do next?

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by dqure040 » Thu Oct 22, 2015 10:25 am
Hi Rich, that's the part I'm having difficulty "visualizing" I understand the 2 ratios, but get to the final ratio with 2 unknowns is my issue.

Filling in numbers, I can see how the solution came to be, but with expressions I can't see it. Normally I'm better with equations, but i guess ratios are a weak point.
Join the discussion

by [email protected] » Thu Oct 22, 2015 10:33 am
Hi dqure040,

This prompt ultimately asks for the fraction of the TOTAL BOXES that were loaded by the DAY workers. Using the information from the last post...

Total boxes loaded by Day workers = (D)(B)
Total boxes loaded by Night workers = (4/5)(D)(3/4)(B) = (12/20)(D)(B)

Total of ALL boxes = (D)(B) + (12/20)(D)(B) = (32/20)(D)(B)

Fraction loaded by the Day workers = (D)(B)/[(32/20)(D)(B)]

The DBs 'cancel out' and we're left with 1/(32/20) = 20/32 = 5/8

Final Answer: E