ramonsa wrote:15. Working alone, R can complete a certain kind of job in 9 hours. R and S, working together at their respective rates, can complete one of these jobs in 6 hours. In how many hours can S, working alone, complete one of these jobs?
(A) 18
(B) 12
(C) 9
(D) 6
(E) 3
Let's assign a "nice" value to the job.
Say, the job is to make 18 widgets (since 9 and 6 both divide nicely into 18).
R can complete the job in 9 hours
In other words, R can make 18 widgets in 9 hours.
This means that machine R's rate is
2 widgets/hour
Together, R and S can complete the job in 6 hours
In other words, R+S can make 18 widgets in 6 hours.
This means their combined rate is
3 widgets/hour
So, working along, Machine S's rate must be
1 widget/hour.
In how many hours can S, working alone, complete one of these jobs?
So, machine S must make 18 widgets, and its rate is 1 widget/hour.
So, it will take
18 hours
Answer:
A
Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com