A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will te project be completed?
A. 18
B. 27
C.26.67
D.16
E.12
OA: 18 days
project
This topic has expert replies
-
- Legendary Member
- Posts: 2467
- Joined: Thu Aug 28, 2008 6:14 pm
- Thanked: 331 times
- Followed by:11 members
B has to work alone for 10 days
In 10 days B will complete 1/30 * 10 = 1/3 of work
So A and B must have worked to complete the remaining 2/3rd of the work
(1/20+1/30) * t = 2/3
t= 8
Total(T) = 10(1/3rd work completed by B) + 8(2/3RD WORK compelted by both A and B)
T = 18
In 10 days B will complete 1/30 * 10 = 1/3 of work
So A and B must have worked to complete the remaining 2/3rd of the work
(1/20+1/30) * t = 2/3
t= 8
Total(T) = 10(1/3rd work completed by B) + 8(2/3RD WORK compelted by both A and B)
T = 18
-
- Master | Next Rank: 500 Posts
- Posts: 179
- Joined: Tue Jan 08, 2008 7:23 pm
- Thanked: 11 times
- GMAT Score:590
taking cue from Cramya
step 1:::::last 10 days B alone will work
step 2:::::first few days A & B both work together at 12 days/work pace(1/20 + 1/30)
now step 1 does 1/3rd work
hence step 2 does 2/3 rd work in how many days?
(2/3) *(12)=8 days
total time = 10 + 8 =18 days
step 1:::::last 10 days B alone will work
step 2:::::first few days A & B both work together at 12 days/work pace(1/20 + 1/30)
now step 1 does 1/3rd work
hence step 2 does 2/3 rd work in how many days?
(2/3) *(12)=8 days
total time = 10 + 8 =18 days