Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Product X

Expert replies
by deepoe » Thu Feb 26, 2009 4:01 am
A company makes product X. One machine produce 100 Product X in 1 hour.
The 2nd machine produce 150 Product X in 1 hour. How many time, in Minutes will both machine produce 300 Product X?
Join the discussion
Source: — Problem Solving |

by scoobydooby » Thu Feb 26, 2009 4:14 am
72 minutes

no of products manufactured by machine I & II in 1 hr or 60 mns=100+150=250
to make 300 products therefore they would take 60/250*300=72 minutes
Join the discussion

by DanaJ » Thu Feb 26, 2009 4:27 am
Notice that, if both machines work at the same time, they make 250 pieces in one hour. This means that we need to find the time it takes for both machines to make 50 pieces.
Again, notice that the second machine makes 50% more pieces in the same time. So let's say:
a = number of pieces made by the first machine
b = number of pieces made by the second machine = 1.5*a
You get that a + 1.5a = 50 or that 2.5a = 50, with a = 20.
To find out the time it takes machine 1 to make 20 pieces, we need to remember that it takes 1 hour to make 100 pieces. This means that it will take 20/100 or one fifth of an hour to make 20 pieces.

So the whole thing will take 1 hour and 12 minutes. or 72 minutes.
Join the discussion

by BuckeyeT » Thu Feb 26, 2009 6:02 am
deepoe-

This should be a simple work problem. Remember,
1/x + 1/y ... = completes/time

Usually, you see these problems as "John completes a job in 5 hours, Mary completes the same job in 2 hours..."

Or, you might see, "Machine A completes a job in... Machine B completes a job in..."

Same concept here.
1/(1/100) + 1/(1/150) = 250/1 or 250 units produced/hour.

We know that 300 units is a 20% increase over 250 units (or 1/5 increase). So, it should take 1 hour + (1 hr)(1/5) =
1 hr + 1/5 hr or 1 hr 12 min.

Quickly converted, that's 72 minutes.