A & B working alone can do a work in 9 and 12 days respectavily. If they work for a day alternately, A beginning, in how many days the work will be completed?
Ans: 41/4 days.
Ans: 41/4 days.
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
Redeem
Scott Woodbury-Stewart’s private virtual classroom — 400 hours of master-class video lessons for the GMAT Focus Edition.
Let the job = 36 units.rrobiinn wrote:A & B working alone can do a work in 9 and 12 days respectavily. If they work for a day alternately, A beginning, in how many days the work will be completed?
Ans: 41/4 days.