BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

PETER TOM JOHN WORK, MGMAT sum

Expert replies
by rb90 » Tue Oct 12, 2010 10:57 am
Tom, working alone, can paint a room in 6 hours. Peter and John, working independently, can paint the same room in 3 hours and 2 hours, respectively. Tom starts painting the room and works on his own for one hour. He is then joined by Peter and they work together for an hour. Finally, John joins them and the three of them work together to finish the room, each one working at his respective rate. What fraction of the whole job was done by Peter?

(A)1/9
(B)1/6
(C)1/3
(D)7/18
(E)4/9

Please explain the working. OA is E
Join the discussion
Source: — Problem Solving |

by shovan85 » Tue Oct 12, 2010 11:03 am
Assume that Tom, Peter and John have worked for x hours to finish the remaining work.
This implies that Tom worked for 2+x hours, Peter worked for 1+x hours and John worked for x hours to complete the work.

So 1/6 * (2+x) + 1/3 * (1+x) + 1/2 * x = 1 (the sum of fractions of work completed by the 3 is equal to the entire work)

Solving for x, x = 1/3

Hence the fraction of work x
Tom completed is 1/6 * (2 + 1/3) = 1/6 * 7/3 = 7/18
Peter completed is 1/3 * (1 + 1/3) = 1/3 * 4/3 = 4/9
John completed is 1/2 * 1/3 = 1/6

Hence the answer is 4/9.
Join the discussion

by rb90 » Tue Oct 12, 2010 11:21 am
BRILLIANT EXPLANATION. THANKS SO MUCH! BEST OF LUCK FOR YOUR GMAT!
Join the discussion

by shovan85 » Tue Oct 12, 2010 11:30 am
rb90 wrote:BRILLIANT EXPLANATION. THANKS SO MUCH! BEST OF LUCK FOR YOUR GMAT!
Thanks!!!
Join the discussion

by GMATGuruNY » Tue Oct 12, 2010 12:44 pm
rb90 wrote:Tom, working alone, can paint a room in 6 hours. Peter and John, working independently, can paint the same room in 3 hours and 2 hours, respectively. Tom starts painting the room and works on his own for one hour. He is then joined by Peter and they work together for an hour. Finally, John joins them and the three of them work together to finish the room, each one working at his respective rate. What fraction of the whole job was done by Peter?

(A)1/9
(B)1/6
(C)1/3
(D)7/18
(E)4/9

Please explain the working. OA is E
Another approach would be to plug in a value for the room. Let room = 54.

Rate for T = 54/6 = 9/hr.
Rate for P = 54/3 = 18/hr.
Rate for J = 54/2 = 27/hr.

T works for 1 hour = 9*1 = 9.
Remaining work = 54-9 = 45.

T works for 1 hour = 9*1 = 9.
P works for 1 hour = 18*1 = 18.
Remaining work = 45-9-18 = 18.

Combined rate for T+P+J = 9+18+27 = 54/hr.
Time for T+P+J to finish = 18/54 = 1/3 of an hour.
Work done by P = 18 * 1/3 = 6.

Total work for P = 18+6 = 24.
Fraction of work by P = 24/54 = 4/9.

The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion