Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Percents

Expert replies
by Nightmare » Wed May 08, 2013 10:38 am
A,B,C can do a piece of work in 36,54,and 72 days respectively. they started the work but A left 8 days before the completion of the work while B left 12 days before the completion. the number of days for which c worked is?
Join the discussion
Source: — Problem Solving |

by ygdrasil24 » Wed May 08, 2013 10:55 am
You may find number of approaches for such questions. I personally find below method to be shortest.
A=36
B=24
C=72.

Take LCM of these numbers to get 18X12.
So A will finish 18X12/36=6 units in 1 day, similarly B=4 units, C=3 units.
Let total work to be completed is 18X12(This is imp number to choose)
Let C worked for x days
so A worked for x-8, B for x-12, C for x
so A's Rate X Days Worked + .... = total work
6(x-8)+4(x-12)+3x=18X12, solve for x to get 24.

I know this method works well, but I have a general question , is it OK to assume two values in one linear equation, here we assumed, 18X 12 and x, had it been ratio or similar, the assumed expression might have got canceled.Please comment.
Join the discussion

by Atekihcan » Wed May 08, 2013 11:22 am
In one day,
  • A does 1/36 of the work
    B does 1/54 of the work
    C does 1/72 of the work

    Together all three of them does (1/36 + 1/54 + 1/72) = (1/18)*(1/2 + 1/3 + 1/4) = (1/18)*(6 + 4 + 3)/12 = 13/12*18
A and C together worked for (12 - 8) = 4 days.
In these 4 days, they completed 4*(1/36 + 1/72) = 4*(2/72 + 1/72) = 4*3/72 = 12/72 of the work

C alone worked for 8 days.
In these 8 days, C completed 8/72 of the work.

So, in last 12 days (12/72 + 8/72) = 20/72 of the work was done.
Hence, the rest of the work, i.e. (1 - 20/72) = 52/72 of the work was done by all of the together.

Now, all of the together takes 12*18/13 days to complete the job.
So, they will take (12*18/13)*(52/72) = 12 days to complete 52/72 of the work.

So, C worked for (12 + 12) = 24 days.