BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Pat took "N" whole days to complete the project. I

Expert replies
by swerve » Wed May 23, 2018 10:03 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

Pat took "N" whole days to complete the project. If the dash represents the digit which has been omitted, then which of the following could be the number of hours that he took to complete the project?

A. 6_98
B. 6_36
C. 6_50
D. 6_90
E. 8_62

The OA is B.

Please, can anyone explain this PS question for me? I tried to solve it but I can't get the correct answer. I need help. Thanks.
Join the discussion
Source: — Problem Solving |

by [email protected] » Wed May 23, 2018 9:30 pm
Hi swerve,

We're told that Pat took "N" whole days to complete the project and that one of the answers represents the value of N (with the dash representing a digit which has been omitted from the 4-digit value of N). We're asked which of the following COULD be the value of N. While this question might look a bit weird, it's built on a specific 'rule of division' that you can use to quickly answer the question.

To start, since we're dealing with WHOLE days, the total number of hours MUST be a multiple of 24. By extension, any number that is a multiple of 24 is ALSO a multiple of 4, so we can use the 'rule of 4' to determine which answers are multiples of 4 and which are not.

For a number to be divisible by 4, the last 2 digits of the number must for a number that is divisible by 4. For example:

112 IS divisible by 4 because '12' is divisible by 4.
115 is NOT divisible by 4 because '15' is not divisible by 4.

Of the 5 answers, only one of them has a 'last 2 digits' that is divisible by 4: "6_36" (since 36 is divisible by 4). Since this is the only answer that fits that pattern, it must be the answer.

Final Answer: B

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image
Join the discussion

by Scott@TargetTestPrep » Thu May 24, 2018 5:03 pm
swerve wrote:Pat took "N" whole days to complete the project. If the dash represents the digit which has been omitted, then which of the following could be the number of hours that he took to complete the project?

A. 6_98
B. 6_36
C. 6_50
D. 6_90
E. 8_62
Since there are 24 hours in a day, the number needs to be divisible by 24. Any number divisible by 24 must also be divisible by 4. A number is divisible by 4 when the last two digits of that number are divisible by 4. Since 36/4 = integer, 6_36 is the correct answer.

Answer: B

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion

by deloitte247 » Fri May 25, 2018 11:55 am
Total number of hours = N * 24
= 24w
So the total number of hours has to be a multiple of 24 hence it is also divisible by 4.
We eliminate the options by finding the number divisible by 4.
Since all options have the last 2 digits we check the divisible by 4.
Option A= 98 is not divisible by 4 (wrong)
Option B= 36 divisible by 4 (Right)
Option C= 50 is not divisible by 4 (Wrong)
Option D= 90 is not divisible by 4 (Wrong)
Option E= 62 not divisible by 4 (Wrong)

Option B is the correct answer.
Join the discussion