Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

OG2015 PS A project scheduled to

Expert replies
by lionsshare » Fri Sep 08, 2017 3:08 pm
A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?

(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430

OA: A

Anyone could please help in explaining the solution. Thanks.
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Fri Sep 08, 2017 11:43 pm
lionsshare wrote:A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?

(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430

OA: A

Anyone could please help in explaining the solution. Thanks.
Budget for 12 months = $12,600
Monthly allocations = $12,600/12 = $1050

Thus, budget for 4 months = 4*$1050 = $4200

Thus, the project was $4,580 − $4,200=$380 over budget for the first 4 months.

The correct answer: A

Hope this helps!

Download free ebook: Manhattan Review GMAT Quantitative Question Bank Guide

-Jay
_________________
Manhattan Review GMAT Prep

Locations: New York | Jakarta | Nanjing | Berlin | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by Jeff@TargetTestPrep » Mon Mar 12, 2018 10:35 am
lionsshare wrote:A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?

(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430
We know that our yearly budget must be divided into 12 EQUAL monthly allocations, so we need to divide $12,600 by 12. This will give us the amount of each monthly allocation. We have:

$12,600/12 = $1,050

Thus, $1,050 should be spent PER MONTH on the project. Therefore, after 4 months, 4 x $1,050 = $4,200 should have been spent on the project.

However, we are told that $4,580 was actually spent, so the project was over budget by:

$4,580 – $4,200 = $380

Answer: A